DeSpain Solar Project
236.17 MW generation in Kinney, TX · In queue since December 2021 · Proposed COD December 2027
236.17 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
Projected COD moved
3 times
May 2024 → Jun 2028
Net change
+49 months
first report to latest
Capacity
236 MW
unchanged in the reports
Latest stage
Screening started
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Research sources and reasoning (8 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-24inr0182
- cleanview.co/power-projects/planned/solar-farms/texas/24INR0182/despain-solar-project
- ercotqueue.com/project/24INR0182
- renewablesinfo.org/project/ercot-24inr0182-despain-solar-project
- infrasure.ai/plant/66421-despain-solar
- cleanview.co/power-projects/developers/gransolar
- renewablesinfo.org/plant/66421-despain-solar
- ercotqueue.com/developer/gransolar-texas-thirteen-llc
Commercial operation date: LBNL queue snapshot shows proposed COD of December 2027. No independent news sources or press releases found to confirm or contradict this date; aggregator sites simply echo the LBNL filing.
Developer: LBNL filing entity is 'Gransolar Texas Thirteen LLC', a project-specific shell. Result 11 (renewablesinfo.org) identifies parent as 'Gransolar Group (GRS)', the operating company behind multiple Texas projects.
Status: LBNL status is 'active' at Facility Study stage with no IA date. Multiple aggregator sources confirm active queue position but note early-stage status and low completion likelihood.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The DeSpain Solar Project is a proposed 236.17 MW solar photovoltaic generation project in Kinney County, Texas. It is being developed by Gransolar Texas Thirteen LLC and would connect to the grid at the 7425 Odlaw Switch 138kV point of interconnection. The project is a standalone solar facility with no battery storage or other generation components.
The project entered the Electric Reliability Council of Texas (ERCOT) interconnection queue on December 5, 2021, under queue ID ERCOT-24INR0182. Its proposed commercial operation date is December 15, 2027. In the interconnection process, it has reached the Facility Study stage, and its current queue status is listed as suspended. The project is linked to an entry in U.S. Energy Information Administration records, Despain Solar (EIA plant ID 66421), with a match confidence of 0.83.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Kinney
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Thirteen LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7425 Odlaw Switch 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- POI Substation
- Odlaw Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
DeSpain Solar Project
Data-driven briefing on DeSpain Solar Project — fleet, generation, financial, and news signals.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.