Tejano Storage
152.31 MW storage in Victoria, TX · In queue since March 2022 · Proposed COD July 2029
152.31 MW
Capacity
1
Components
Battery
4y 4m
In Queue
Facility Study
IA Phase
COD target: 2029
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
IA date added March 27, 2025 per Interconnection.fyi newsletter
sourceTejano Storage, LLC is proposing a 152 MW battery storage project called Tejano Storage in Victoria County, Texas. The project is located within the ERCOT region and entered the ERCOT interconnection queue as entry ERCOT-24INR0168 on March 30, 2022. The proposed commercial operation date is July 1, 2029. The project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 152 MW of battery storage capacity. Recent news coverage indicates industry interest in the Tejano Storage development.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tejano Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 8125 Lolita - 8172 Victoria
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Lolita Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Tejano StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.