Lupinus Storage 2 (ERCOT-24INR0155) — Project Summary

Queue ID
ERCOT-24INR0155
Capacity
124.55 MW
Technology
Solar+Battery
Status
active
Location
Franklin, TX
Region
ERCOT
Developer
Lupinus Solar 2, LLC
IA Status
IA Executed

Lupinus Storage 2

ERCOT-24INR0155BetaActiveBatteryBatteryERCOTLBNL + Live

124.55 MW generation in Franklin, TX · In queue since December 2021 · Proposed COD April 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

124.55 MW

Capacity

1

Components

Battery

4y 11m

In Queue

IA Executed

IA Phase

Signed Mar 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 3m

IA → COD

2y 1m

Total Duration

3y 3m

Construction75%
Queue EntryDec 13, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMar 4, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-04-03

Queue history
24INR0155 · 53 monthly ERCOT reports, May 2022 – Sep 2026

Projected COD moved

3 times

Dec 2024 → Apr 2027

Net change

+28 months

first report to latest

Capacity

123 → 125 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 13, 2021
Facilities study approvedMar 17, 2026
Interconnection agreement signedMar 4, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2027
From queue filing
Developer in saved assessment
Sunraycer Renewables LLC
Filed as Lupinus Solar 2, LLC
Status at research time
IA Executed
IA Executed (2025-03-04) — Construction started March 2026, $901M financing closed May 2026 for portfolio including this project
Financing
Secured
$901M financing closed May 2026 for portfolio (Eagle Springs, Lupinus 1, Lupinus 2) from five banks; projects have PPAs with Google

Milestones in this assessment

IA executedMar 4, 2025

IA executed with Oncor Electric Delivery Company LLC

interchange.puc.texas.gov
GroundbreakingMar 17, 2026

Construction started on Lupinus I & II and Eagle Springs projects

prnewswire.com
Financing closeMay 2026

$901M financing closed for portfolio including Lupinus 2, backed by five major lenders with Google PPAs

pv-magazine-usa.com
COD targetApr 3, 2027Latest in this assessment

LBNL proposed COD

interconnection.fyi
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. prnewswire.com/news-releases/sunraycer-celebrates-start-of-construction-of-lupinus-i--ii-and-eagle-springs-solar--storage-projects-in-texas-302715699.html
  2. pv-magazine-usa.com/2026/05/15/sunraycer-renewables-closes-901-million-financing-for-473-mwh-bess-portfolio-in-texas/
  3. indexbox.io/blog/sunraycer-renewables-secures-901m-financing-for-texas-solarstorage-projects/
  4. renewablesnow.com/news/sunraycer-kicks-off-works-at-three-texas-solar-plus-storage-sites-1291510/
  5. interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2427

Commercial operation date: LBNL proposes 2027-04-03 COD. Construction started March 2026 per press release, making 2027 plausible. No contradicting sources found.

Developer: LBNL filing entity is 'Lupinus Solar 2, LLC' (project shell). Multiple press releases and financing announcements identify Sunraycer Renewables LLC as the actual developer, owner, and operator of the Lupinus portfolio.

Status: LBNL shows IA executed March 2025. Press releases confirm construction kickoff March 17, 2026 and financing close ~May 2026, consistent with active development post-IA.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Lupinus Storage 2 is a proposed 122.92 MW battery storage project located in Franklin County, Texas. The project, developed by Lupinus Solar 2, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0155, with a queue entry date of December 13, 2021. The proposed commercial operation date is April 3, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 1794 Monticello Tap Substation 138 kV. The project consists solely of battery storage, with a total capacity of 122.92 MW.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Franklin

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Lupinus Solar 2, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Hagansport Switch (old Monticello Tap bus# 1794)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.