Lupinus Solar 1
162.31 MW hybrid in Franklin, TX · In queue since December 2021 · Proposed COD September 2027
162.31 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Phase
Signed Jun 2025
Queue → IA
3y 6m
IA → COD
2y 3m
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-09-13
Lupinus Solar 1 is a proposed solar generation project with a total capacity of 164.86 MW. The project, located in Franklin County, Texas, is being developed by Lupinus Solar, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0150, with a queue entry date of December 8, 2021, and a proposed commercial operation date of September 13, 2027. The project's interconnection status is currently in the Facility Study phase.
The development project has been featured in recent news coverage related to deals and development.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Franklin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lupinus Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 11699 Woodard Switch - 1695 Monticello SES
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Lupinus Solar 1Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.