Lupinus Solar 1
162.31 MW hybrid in Franklin, TX · In queue since December 2021 · Proposed COD September 2027
162.31 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Phase
Signed Jun 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 6m
IA → COD
2y 3m
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-09-13
Projected COD moved
3 times
Dec 2024 → Sep 2027
Net change
+33 months
first report to latest
Capacity
165 → 162 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Construction start announced for Lupinus I & II and Eagle Springs projects
prnewswire.com$901M financing package closed for Lupinus I & II and Eagle Springs projects (479.5 MWac total)
indexbox.ioProposed commercial operation date per LBNL queue filing
prnewswire.comResearch sources and reasoning (4 recorded sources)
high confidence at research time
- prnewswire.com/news-releases/sunraycer-celebrates-start-of-construction-of-lupinus-i--ii-and-eagle-springs-solar--storage-projects-in-texas-302715699.html
- indexbox.io/blog/sunraycer-renewables-secures-901m-financing-for-texas-solarstorage-projects/
- pv-tech.org/sunraycer-google-ink-ppas-for-400mwac-lupinus-solar-project-in-texas/
- energy-storage.news/e-storage-sunraycer-enter-agreements-for-texas-bess-projects-totalling-503mwh/
Commercial operation date: LBNL queue shows proposed COD of 2027-09-13. Construction started March 2026 per Sunraycer press release, which is consistent with a 2027 online date. No conflicting COD found in research.
Developer: LBNL filing entity is 'Lupinus Solar, LLC' (project shell). Multiple 2026 press releases identify Sunraycer Renewables as the actual developer and owner operating the project.
Status: LBNL shows IA executed June 2025. Sunraycer announced construction start March 17, 2026 and secured $901M financing package (announced ~2 weeks ago per IndexBox) for this and two other Texas projects.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Lupinus Solar 1 is a proposed solar generation project with a total capacity of 164.86 MW. The project, located in Franklin County, Texas, is being developed by Lupinus Solar, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0150, with a queue entry date of December 8, 2021, and a proposed commercial operation date of September 13, 2027. The project's interconnection status is currently in the Facility Study phase.
The development project has been featured in recent news coverage related to deals and development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Franklin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lupinus Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 11699 Woodard Switch - 1695 Monticello SES
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.