Calpine Guadalupe Peakers
450 MW generation in Guadalupe, TX · In queue since November 2021 · Proposed COD May 2030
450 MW
Capacity
1
Components
Gas
5 years
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-05-30
Projected COD moved
3 times
May 2024 → May 2030
Net change
+72 months
first report to latest
Capacity
450 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-24inr0145
- ercotqueue.com/project/24INR0145
- cleanview.co/power-projects/planned/natural-gas-power-plants/texas/24INR0145/calpine-guadalupe-peakers
- gem.wiki/Guadalupe_generating_station
- app.nrgmap.com/queues/ercot-24inr0145
Commercial operation date: Only the LBNL/ERCOT filing date (proposed COD 2030-05-30) is specific to this project, and the aggregator sites (interconnection.fyi, cleanview) repeat it. The news-extracted 2026-06 COD and the Calpine 'operational before summer 2026' release describe the Freestone Energy Center Expansion in Freestone County, not Guadalupe Peakers, so I excluded them.
Developer: The LBNL filer is a project LLC. The project is branded 'Calpine Guadalupe Peakers' and Global Energy Monitor places it next to Calpine's Guadalupe Energy Center, so Calpine is the operating parent. The Exelon-to-Wayzata sale in the news facts is a 2014 transaction on other Texas plants and does not apply here.
Status: LBNL, interconnection.fyi, ercotqueue.com and NRG Map all show the project as active in the queue. No source documents a groundbreaking, an IA, or a withdrawal for this project.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Calpine Guadalupe Peakers project is a proposed 450 MW gas-fired generation project located in Guadalupe County, Texas. The developer is Guadalupe Peaking Energy Center, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0145, with a queue entry date of November 15, 2021, and a proposed commercial operation date of May 23, 2027. Its interconnection status is currently in the Facility Study phase.
The Calpine Guadalupe Peakers project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Guadalupe
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Guadalupe Peaking Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7044 Marion 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- GUADG_CC1
- POI Substation
- Marion Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.