Eagle Springs Storage
33.14 MW generation in Delta, TX · In queue since October 2021 · Proposed COD March 2027
33.14 MW
Capacity
1
Components
Battery
5y 1m
In Queue
IA Executed
IA Phase
Signed Apr 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 6m
IA → COD
2y 11m
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-03-29
Projected COD moved
6 times
Dec 2024 → Mar 2027
Net change
+27 months
first report to latest
Capacity
61 → 34 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Eagle Springs Storage is a proposed 55.1 MW battery storage project located in Delta County, Texas. The project, developed by Eagle Springs Solar, LLC, is currently in the ERCOT interconnection queue as entry ERCOT-24INR0136, with a queue entry date of October 18, 2021. The proposed commercial operation date is December 31, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The Eagle Springs Storage project has been featured in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Delta
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Eagle Springs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Lake Creek Substation (#6835) – Enloe Switching station (#6834) 138 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SCES_UNIT1
- POI Substation
- Lake Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Eagle Springs StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.