Zelus BESS (ERCOT-24INR0131) — Project Summary

Queue ID
ERCOT-24INR0131
Capacity
201.03 MW
Technology
Battery
Status
active
Location
Zapata, TX
Region
ERCOT
Developer
BRP Zelus BESS LLC
IA Status
Facility Study

Zelus BESS

ERCOT-24INR0131BetaActiveBatteryERCOTLBNL + Live

201.03 MW storage in Zapata, TX · In queue since December 2021 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

201.03 MW

Capacity

1

Components

Battery

4y 11m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6 years

Facilities Study50%
Queue EntryDec 20, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Queue history
24INR0131 · 58 monthly ERCOT reports, Dec 2021 – Sep 2026

Projected COD moved

2 times

Feb 2024 → Dec 2027

Net change

+46 months

first report to latest

Capacity

207 → 201 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 20, 2021

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 2027
From queue filing
Developer in saved assessment
ENGIE
Filed as BRP Zelus BESS LLC
Status at research time
Active
Active — Facility Study stage, no IA executed yet. Third-party analysis (ercotqueue.com) assigns 5% build-chance, indicating early-stage development with no construction timeline.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. live.euronext.com/sites/default/files/company_press_releases/attachments/2026/02/26/cpr03_lesechos_16165_1391055_Liste_des_filiales_et_participations_2025.pdf
  2. zonebourse.com/cours/action/ENGIE-4995/actualite/ENGIE-Liste-des-filiales-et-participations-2024-49180170/
  3. zonebourse.com/actualite-bourse/engie-liste-des-filiales-et-participations-2025-ce7e5cd8da88ff2d
  4. webdisclosure.com/press-release/engie-epa-engi-liste-des-filiales-et-participations-2023-pdiZOfwMwvi
  5. ercotqueue.com/project/24INR0131

Commercial operation date: LBNL queue snapshot shows proposed COD of December 2027. No independent news sources or press releases found to confirm or contradict this date.

Developer: LBNL filing entity is 'BRP Zelus BESS LLC', a project-specific LLC. ENGIE subsidiary filings from 2023-2025 consistently list 'BRP Zelus BESS LLC' as a 100%-owned subsidiary under 'Intégration globale', confirming ENGIE as the parent operating company.

Status: LBNL status is 'active' at Facility Study stage with no IA date. No news of construction start, financing, or permitting milestones found in search results.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Zelus BESS project is a proposed 201.03 MW battery storage project located in Zapata County, Texas. The developer is BRP Zelus BESS LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0131, with a queue entry date of December 20, 2021, and a proposed commercial operation date of December 1, 2027. The project's interconnection status is currently in the Facility Study phase.

The point of interconnection for the Zelus BESS project is the 138 kV Zapata Substation (#8299; AEP). The project has appeared in recent news coverage regarding energy storage developments in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Zapata

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Zelus BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

the 138 kV Zapata Substation (#8299; AEP)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
BRP_ZPT1_RN
POI Substation
Zapata Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.