High Noon Solar
182 MW hybrid in Hill, TX · In queue since November 2021 · Proposed COD May 2028
182 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Phase
Signed May 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 6m
IA → COD
4 years
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-05-09
Projected COD moved
4 times
Dec 2024 → May 2028
Net change
+41 months
first report to latest
Capacity
182 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT
assets.comptroller.texas.govResearch sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: LBNL proposes 2028-05-09 COD, but all search results reference a different 'High Noon Solar' project in Wisconsin (Columbia County, 300MW, owned by MGE/Invenergy), not the Texas ERCOT project. The Texas PDF confirms Enel Green Power as developer for a Hill County TX project, but provides no COD update. No current news exists for the ERCOT-24INR0124 project.
Developer: LBNL filing entity is 'High Noon Solar Project, LLC'. Texas Comptroller document (Sep 2022) explicitly states 'High Noon Solar Project, LLC, a member of the Enel Green Power North America group', confirming the shell-LLC structure with Enel as parent operator.
Status: LBNL shows 'active' status with IA executed 2024-05-03. No news coverage of the Texas project exists post-IA execution; all search results reference the unrelated Wisconsin project of the same name.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
High Noon Solar is a proposed 182 MW solar generation project located in Hill County, Texas. The developer is High Noon Solar Project, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0124, with a queue entry date of November 3, 2021, and a proposed commercial operation date of May 9, 2028. The project's Interconnection Agreement (IA) was executed on May 3, 2024.
The High Noon Solar project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
High Noon Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 445 Yates - 444 Covington
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.