High Noon Solar (ERCOT-24INR0124) — Project Summary

Queue ID
ERCOT-24INR0124
Capacity
182 MW
Technology
Solar+Battery
Status
active
Location
Hill, TX
Region
ERCOT
Developer
High Noon Solar Project, LLC
IA Status
IA Executed

High Noon Solar

ERCOT-24INR0124BetaActiveSolarBatteryERCOTLBNL + Live

182 MW hybrid in Hill, TX · In queue since November 2021 · Proposed COD May 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

182 MW

Capacity

1

Components

Solar

5 years

In Queue

IA Executed

IA Phase

Signed May 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 6m

IA → COD

4 years

Total Duration

2y 6m

Construction75%
Queue EntryNov 3, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 3, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-05-09

Queue history
24INR0124 · 59 monthly ERCOT reports, Nov 2021 – Sep 2026

Projected COD moved

4 times

Dec 2024 → May 2028

Net change

+41 months

first report to latest

Capacity

182 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 3, 2021
Interconnection agreement signedMay 3, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
—
Developer in saved assessment
Enel Green Power North America
Filed as High Noon Solar Project, LLC
Status at research time
Active
Active — IA executed May 2024, no construction or financing announcements found in public record
Financing
Not recorded

Milestones in this assessment

IA executedMay 3, 2024Latest in this assessment

Interconnection Agreement executed with ERCOT

assets.comptroller.texas.gov
Research sources and reasoning (1 recorded sources)

low confidence at research time

  1. assets.comptroller.texas.gov/ch313/1977/1977-covington-high-appsupp2.pdf

Commercial operation date: LBNL proposes 2028-05-09 COD, but all search results reference a different 'High Noon Solar' project in Wisconsin (Columbia County, 300MW, owned by MGE/Invenergy), not the Texas ERCOT project. The Texas PDF confirms Enel Green Power as developer for a Hill County TX project, but provides no COD update. No current news exists for the ERCOT-24INR0124 project.

Developer: LBNL filing entity is 'High Noon Solar Project, LLC'. Texas Comptroller document (Sep 2022) explicitly states 'High Noon Solar Project, LLC, a member of the Enel Green Power North America group', confirming the shell-LLC structure with Enel as parent operator.

Status: LBNL shows 'active' status with IA executed 2024-05-03. No news coverage of the Texas project exists post-IA execution; all search results reference the unrelated Wisconsin project of the same name.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

High Noon Solar is a proposed 182 MW solar generation project located in Hill County, Texas. The developer is High Noon Solar Project, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0124, with a queue entry date of November 3, 2021, and a proposed commercial operation date of May 9, 2028. The project's Interconnection Agreement (IA) was executed on May 3, 2024.

The High Noon Solar project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Hill

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

High Noon Solar Project, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 445 Yates - 444 Covington

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.