Two Rivers Solar
208.7 MW generation in Milam, TX · In queue since July 2021 · Proposed COD June 2029
208.7 MW
Capacity
1
Components
Solar
5y 4m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-07
Projected COD moved
5 times
Sep 2024 → Jun 2029
Net change
+57 months
first report to latest
Capacity
214 → 209 MW
changed in the reports
Latest stage
Cancelled
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Jul 2026 queue source. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
Commercial operation date: LBNL proposes 2029-06-07 COD. All search results reference a different 'Two Rivers Solar' project in New York (Brasher/Massena, 200 MW, developer Boralex) with 2028 target. No news found for the Texas ERCOT project (Milam County, 208.7 MW, Two Rivers Solar LLC). LBNL date stands as only source.
Developer: No research findings for the Texas project. LBNL filing entity 'Two Rivers Solar, LLC' is the only available source. All search results reference unrelated NY project by Boralex.
Status: LBNL status 'active' at Facility Study stage. No contradicting evidence found; search results all reference different project in New York.
About
Generated Apr 10, 2026 · Predates Jul 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Two Rivers Solar is a proposed solar generation project located in Milam County, Texas, with a total capacity of 219.35 MW. Developed by Two Rivers Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0099, with a queue entry date of July 27, 2021. The proposed commercial operation date is June 7, 2029, and the interconnection agreement status is currently in the Facility Study phase.
The proposed project is linked to the existing Two Rivers Solar operating plant (EIA plant ID 68198). The Two Rivers Solar project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Two Rivers Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 64 Milano – 32 Robertson
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Branchville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Two Rivers Solar
Data-driven briefing on Two Rivers Solar — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.