Pisgah Ridge Solar 2
101.89 MW hybrid in Navarro, TX · In queue since July 2021 · Proposed COD March 2029
101.89 MW
Capacity
1
Components
Solar
5y 4m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-31
Projected COD moved
5 times
Sep 2024 → Mar 2029
Net change
+54 months
first report to latest
Capacity
102 MW
unchanged in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2025-05·Duke Energy Renewables→Deriva Energy (Brookfield portfolio company)mercomcapital.com
Milestones in this assessment
Duke unit starts construction on 250MW Pisgah Ridge project with PPAs secured
pv-magazine-usa.com250MW Pisgah Ridge solar project now operating, selling power to three corporate offtakers
bizjournals.comDuke Energy Renewables rebranded to Deriva Energy under Brookfield ownership
mercomcapital.comDeriva Energy completes $127M financing for solar and wind portfolio
mercomcapital.comResearch sources and reasoning (7 recorded sources)
high confidence at research time
- power-technology.com/projects/pisgah-ridge-solar-project-texas-us/
- pv-magazine-usa.com/2022/03/03/duke-energy-250mw-solar-project-finds-offtaker-in-major-us-retailer/
- bizjournals.com/charlotte/news/2023/03/08/duke-energy-sustainable-solutions-solar-texas.html
- mercomcapital.com/deriva-energy-secures-127-m-financing-solar-and-wind-projects/
- pv-magazine-usa.com/2021/06/07/sunrise-brief-with-ppas-in-hand-duke-unit-starts-work-on-250-mw-texas-solar-project/
- cleanview.co/power-projects/planned/solar-farms/texas/24INR0086/pisgah-ridge-solar-2
- comptroller.texas.gov/economy/docs/active-list.xlsx
Commercial operation date: The Business Journals (March 2023) reports the 250MW Pisgah Ridge solar project is 'now operating in Texas.' LBNL's 2029 COD for the 102MW 'Pisgah Ridge Solar 2' appears to be a separate phase or expansion, but the main project is already online, making the 2029 date likely stale or referring to a different component.
Developer: Power Technology and pv magazine (2021-2022) identify Duke Energy Sustainable Solutions as developer. Mercom Capital (May 2025) reports Duke Energy Renewables rebranded to Deriva Energy and is now a Brookfield portfolio company. The LBNL filing entity is a project LLC.
Status: LBNL status 'active' is accurate for this queue position. The 250MW main project is operational (March 2023), but this 102MW component appears to be a separate phase still in interconnection studies.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Pisgah Ridge Solar 2 is a proposed solar generation project located in Navarro County, Texas, within the ERCOT region. The project, developed by Pisgah Ridge Solar 2, LLC, has a total capacity of 101.89 MW. It consists solely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0086, with an original queue entry date of July 14, 2021. The proposed commercial operation date is December 1, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 68091 Navarro - 46020 Limestone. The project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pisgah Ridge Solar 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 68091 Navarro - 46020 Limestone
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Navarro Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Pisgah Ridge Solar 2Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.