Blue Bird Solar
773 MW generation in Johnson, TX · In queue since November 2021 · Proposed COD December 2028
773 MW
Capacity
1
Components
Solar
4y 8m
In Queue
IA Executed
IA Phase
Signed Jan 2024
Queue → IA
2y 2m
IA → COD
4y 11m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-15
Generation Interconnection Agreement executed between Oncor Electric Delivery Company LLC and Gigawatt Solar LLC
sourceBlue Bird Solar is a proposed solar generation project with a total capacity of 1004 MW, located in Johnson County, Texas. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0075, with a queue entry date of November 10, 2021, and a proposed commercial operation date of June 27, 2028.
The development project is currently listed as active in the queue. Blue Bird Solar has been the subject of recent news coverage, with 10 articles related to the project appearing in industry, deals, grid, and development news categories.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Johnson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gigawatt Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1880 Rocky Creek - 1898 Mitchell Bend Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.