Blue Bird Solar
773 MW generation in Johnson, TX · In queue since November 2021 · Proposed COD December 2028
773 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Phase
Signed Jan 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 2m
IA → COD
4y 11m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-15
Projected COD moved
3 times
Dec 2024 → Dec 2028
Net change
+48 months
first report to latest
Capacity
502 → 426 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- johnsoncounty.myopentexas.org/development/bluebird-solar
- citizenportal.ai/articles/8677650/texas/johnson-county/developer-presents-773-mw-bluebird-solar-plan-for-johnson-county-court-hears-timeline-safety-and-decommissioning-commitments
- citizenportal.ai/articles/7885608/Texas/Hidalgo-County/Court-signs-roaduse-agreement-with-Gigawatt-Solar-for-Bluebird-Solar-developer-to-repair-county-roads
- ercotqueue.com/project/24INR0075
- cleanview.co/power-projects/planned/solar-farms/texas/24INR0075/blue-bird-solar-
Commercial operation date: Only the LBNL/ERCOT queue date (2028-12-15) exists. Cleanview's 'Expected online 2028' appears to be derived from the same queue data. No developer press release or financing-backed target was found. The Mar 2026 county presentation covered a timeline, but no date was captured.
Developer: Gigawatt Solar LLC is the LBNL filing entity and signed the Johnson County road-use agreement (Dec 2025). Allium Renewable Energy presented the same 773 MW Bluebird project to the county in Mar 2026 and is listed as applicant, so Gigawatt Solar LLC is most likely Allium's project LLC. No source states the relationship explicitly, so this is an inference. The news-extracted 'Lightsource bp' developer data refers to Briar Creek Solar, a different project, and was discarded.
Status: LBNL and ERCOT trackers list the project as active in the queue. County records show local review is ongoing with no construction start or approval reported. The 'operational' status in the news facts belongs to Briar Creek Solar and does not apply.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Blue Bird Solar is a proposed solar generation project with a total capacity of 1004 MW, located in Johnson County, Texas. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0075, with a queue entry date of November 10, 2021, and a proposed commercial operation date of June 27, 2028.
The development project is currently listed as active in the queue. Blue Bird Solar has been the subject of recent news coverage, with 10 articles related to the project appearing in industry, deals, grid, and development news categories.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Johnson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gigawatt Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1880 Rocky Creek - 1898 Mitchell Bend Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Rocky Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.