Blue Bird Solar (ERCOT-24INR0075) — Project Summary

Queue ID
ERCOT-24INR0075
Capacity
773 MW
Technology
Solar
Status
active
Location
Johnson, TX
Region
ERCOT
Developer
Gigawatt Solar LLC
IA Status
IA Executed

Blue Bird Solar

ERCOT-24INR0075BetaActiveSolarERCOTLBNL + Live

773 MW generation in Johnson, TX · In queue since November 2021 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

773 MW

Capacity

1

Components

Solar

5 years

In Queue

IA Executed

IA Phase

Signed Jan 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 2m

IA → COD

4y 11m

Total Duration

2y 2m

Construction75%
Queue EntryNov 10, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 18, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-12-15

Queue history
24INR0075 · 48 monthly ERCOT reports, Nov 2021 – Sep 2026

Projected COD moved

3 times

Dec 2024 → Dec 2028

Net change

+48 months

first report to latest

Capacity

502 → 426 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 10, 2021
Facilities study approvedMay 18, 2023
Interconnection agreement signedJan 18, 2024
On ERCOT's inactive listDec 2024 – Oct 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 3y 9m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Project statusOperationalLightsource bp · 2023-02-02

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 15, 2028
From queue filing
Developer in saved assessment
Allium Renewable Energy
Filed as Gigawatt Solar LLC
Status at research time
Active
Active, pre-construction. LBNL shows the IA executed 2024-01-18 (ercotqueue.com says IA/FIS pending). Johnson County has only signed a road-use agreement, which is explicitly not project approval, and discussed the project on 2026-03-23. Reported capacity varies by source (426, 773 and 1004 MW).
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. johnsoncounty.myopentexas.org/development/bluebird-solar
  2. citizenportal.ai/articles/8677650/texas/johnson-county/developer-presents-773-mw-bluebird-solar-plan-for-johnson-county-court-hears-timeline-safety-and-decommissioning-commitments
  3. citizenportal.ai/articles/7885608/Texas/Hidalgo-County/Court-signs-roaduse-agreement-with-Gigawatt-Solar-for-Bluebird-Solar-developer-to-repair-county-roads
  4. ercotqueue.com/project/24INR0075
  5. cleanview.co/power-projects/planned/solar-farms/texas/24INR0075/blue-bird-solar-

Commercial operation date: Only the LBNL/ERCOT queue date (2028-12-15) exists. Cleanview's 'Expected online 2028' appears to be derived from the same queue data. No developer press release or financing-backed target was found. The Mar 2026 county presentation covered a timeline, but no date was captured.

Developer: Gigawatt Solar LLC is the LBNL filing entity and signed the Johnson County road-use agreement (Dec 2025). Allium Renewable Energy presented the same 773 MW Bluebird project to the county in Mar 2026 and is listed as applicant, so Gigawatt Solar LLC is most likely Allium's project LLC. No source states the relationship explicitly, so this is an inference. The news-extracted 'Lightsource bp' developer data refers to Briar Creek Solar, a different project, and was discarded.

Status: LBNL and ERCOT trackers list the project as active in the queue. County records show local review is ongoing with no construction start or approval reported. The 'operational' status in the news facts belongs to Briar Creek Solar and does not apply.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Blue Bird Solar is a proposed solar generation project with a total capacity of 1004 MW, located in Johnson County, Texas. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0075, with a queue entry date of November 10, 2021, and a proposed commercial operation date of June 27, 2028.

The development project is currently listed as active in the queue. Blue Bird Solar has been the subject of recent news coverage, with 10 articles related to the project appearing in industry, deals, grid, and development news categories.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Johnson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Gigawatt Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 1880 Rocky Creek - 1898 Mitchell Bend Switch

Data Source

LBNL + Live

DeveloperLightsource bppv magazine USA · 2024-03-14
TransactionTax equitypv magazine USA · 2024-03-14
Deal value$140.0Mpv magazine USA · 2024-03-14
OfftakerBarclayspv magazine USA · 2024-03-14
LenderBarclayspv magazine USA · 2024-03-14
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Rocky Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.