Hyacinth Storage
103.05 MW storage in Harris, TX · In queue since July 2021 · Proposed COD December 2030
103.05 MW
Capacity
1
Components
Battery
5y 4m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-25
Projected COD moved
2 times
Jul 2023 → Dec 2030
Net change
+89 months
first report to latest
Capacity
103 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0073/hyacinth-storage
- interconnection.fyi/projects/state/TX
Commercial operation date: Only LBNL queue data provides a COD target of 2030-12-25. No independent news sources or press releases found to validate or update this date.
Developer: Only LBNL filing identifies 'Hyacinth Storage, LLC' as developer. No news coverage or corporate announcements found to identify a parent company or operating entity behind this project LLC.
Status: LBNL reports 'active' status in Facility Study phase. No news coverage exists to provide ground-truth updates on construction timeline or permitting progress.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Hyacinth Storage is a proposed 103.05 MW battery storage project located in Harris County, Texas. The project, developed by Hyacinth Storage, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0073, with a queue entry date of July 2, 2021. The proposed commercial operation date is December 25, 2030, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists solely of battery storage, with a total capacity of 103.05 MW. The point of interconnection is the 46500 Tomball 345 kV location. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hyacinth Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
46500 Tomball 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Tomball Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.