KEYS HOLLOW STORAGE SLF
— hybrid in Goliad, TX · In queue since June 2021 · Proposed COD March 2028
—
Capacity
0
Components
5y 4m
In Queue
—
IA Status
Signed Oct 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 4m
IA → COD
3y 5m
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-03-10
Keys Hollow Storage SLF (queue ID ERCOT-24INR0068) is a proposed battery energy storage development project located in Goliad County, Texas. The project is being developed by Keys Hollow Solar, LLC and is classified as a hybrid project, with technology components listed as battery energy storage and an additional component categorized as "Other." The provided data does not specify a total capacity or individual component capacities. The project is planned to interconnect at a point identified as a tap on the 345 kV line from Coleto 8164 to Raptor7A 8673.
The project is in the interconnection queue of the Electric Reliability Council of Texas (ERCOT), which it entered on June 17, 2021, and its queue status is listed as active. An interconnection agreement was executed on October 29, 2024, marking an advanced stage in the interconnection process. The proposed commercial operation date is March 10, 2028.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Goliad
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Keys Hollow Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345 KV LINE FROM COLETO 8164 - RAPTOR7A 8673
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about KEYS HOLLOW STORAGE SLFForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.