Roadrunner Crossing BESS SLF
— hybrid in Eastland, TX · In queue since November 2022 · Proposed COD August 2026
—
Capacity
0
Components
3y 11m
In Queue
—
IA Status
Signed Feb 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 3m
IA → COD
1y 6m
Total Duration
2y 3m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2026-08-30
Roadrunner Crossing BESS SLF (queue ID ERCOT-23INR0538) is a proposed battery energy storage development project in Eastland County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Roadrunner Crossing BESS and is classified as a hybrid project. Its listed technology components are battery energy storage and a second component categorized as "Other." The available data does not specify the total capacity or the capacities of the individual components. The project's proposed point of interconnection is the 68051 Reata 354kV substation.
The project entered the ERCOT interconnection queue on November 15, 2022, and its queue status is active. An interconnection agreement was executed on February 15, 2025, marking a significant step in the project's interconnection process. The proposed commercial operation date is August 30, 2026.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Eastland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Roadrunner Crossing BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68051 Reata 354kV
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Roadrunner Crossing BESS SLFForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.