Soda Lake BESS 1 (ERCOT-23INR0501) — Project Summary

Queue ID
ERCOT-23INR0501
Capacity
203.87 MW
Technology
Battery
Status
active
Location
Crane, TX
Region
ERCOT
Developer
Mendoza Trail BESS, LLC
IA Status
IA Executed

Soda Lake BESS 1

ERCOT-23INR0501BetaActiveBatteryERCOTLBNL

203.87 MW storage in Crane, TX · In queue since September 2022 · Proposed COD February 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

203.87 MW

Capacity

1

Components

Battery

4y 2m

In Queue

IA Executed

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 5m

Schedule

9 months past proposed COD

Construction75%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-02-27

Queue history
23INR0501 · 49 monthly ERCOT reports, Aug 2022 – Aug 2026

Projected COD moved

10 times

Jun 2024 → Aug 2026

Net change

+26 months

first report to latest

Capacity

200 → 204 MW

changed in the reports

Latest stage

Commercial operation

last listed Aug 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 2, 2022
Facilities study approvedOct 22, 2024
Interconnection agreement signedAug 20, 2018
Approved for energizationSep 2, 2025
Approved for synchronizationNov 5, 2025
Approved for commercial operationSep 4, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Aug 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Dec 2025
Differs from queue: Feb 27, 2026
Developer in saved assessment
Mendoza Trail BESS, LLC
From queue filing
Status at research time
Active
Active — appears to be in late-stage development or early commissioning phase based on ERCOT operational forecasts showing 2025 online date and one source listing as 'Commissioned'
Financing
Not recorded

Milestones in this assessment

IA executedSep 2, 2022

Interconnection Agreement executed, project entered ERCOT queue

cleanview.co
COD targetDec 17, 2025Latest in this assessment

ERCOT MORA report lists expected commercial operation date of December 17, 2025

ercot.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/23INR0501/soda-lake-bess-1
  2. ercot.com/files/docs/2025/11/06/Capacity-Changes-by-Fuel-Type-Charts_October_2025_PlannedMonthly.xlsx
  3. ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
  4. ercot.com/files/docs/2025/05/02/MORA_July2025.pdf
  5. ercotqueue.com/project/23INR0501

Commercial operation date: LBNL proposed COD is April 2026, but multiple ERCOT operational documents from 2025 show the project listed with 2025 online dates. The ERCOT MORA report from May 2025 lists COD as 12/17/2025, and the November 2025 Capacity Changes chart shows it planned for 2025. One source (ercotqueue.com) lists status as 'Commissioned' with 100% build-chance, suggesting imminent or completed construction.

Developer: All sources consistently identify 'Mendoza Trail BESS, LLC' as the developer. No parent company or operating entity was identified in search results, suggesting this may be the actual operating entity rather than a shell LLC, or the parent company has not been publicly disclosed.

Status: LBNL shows 'Active' with IA Executed status. Recent ERCOT planning documents consistently include the project in 2025 capacity forecasts, and ercotqueue.com lists it as 'Commissioned' with 100% build probability, indicating the project has progressed significantly beyond initial queue status.

About

Saved background

Generated Apr 10, 2026 · Predates Aug 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Soda Lake BESS 1 is a proposed 203.87 MW battery storage project located in Crane County, Texas. The project, developed by Mendoza Trail BESS, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0501. The project entered the interconnection queue on September 2, 2022, with a proposed commercial operation date of February 27, 2026.

The project's Interconnection Agreement (IA) has been executed as of August 20, 2018. The point of interconnection is the 138kV Soda Lake Substation (#76026). Soda Lake BESS 1 has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Aug 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Crane

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Mendoza Trail BESS, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

138kV Soda Lake Substation (#76026)

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SLK_BESS_RN
POI Substation
Soda Lake Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.