Sloan Storage (ERCOT-23INR0464) — Project Summary

Queue ID
ERCOT-23INR0464
Capacity
200.9 MW
Technology
Battery
Status
active
Location
Henderson, TX
Region
ERCOT
Developer
Sloan Energy Storage LLC
IA Status
Facility Study

Sloan Storage

ERCOT-23INR0464BetaActiveBatteryERCOTLBNL + Live

200.9 MW storage in Henderson, TX · In queue since February 2022 · Proposed COD March 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200.9 MW

Capacity

1

Components

Battery

4y 9m

In Queue

Facility Study

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 1m

Schedule

8 months past proposed COD

Facilities Study50%
Queue EntryFeb 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-27

Queue history
23INR0464 · 49 monthly ERCOT reports, Jul 2022 – Sep 2026

Projected COD moved

1 time

Jun 2024 → Mar 2026

Net change

+21 months

first report to latest

Capacity

203 → 201 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 21, 2022
On ERCOT's inactive listNov 2022 – Dec 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Mar 2026
From queue filing
Developer in saved assessment
Sloan Energy Storage LLC
From queue filing
Status at research time
Active
Active — Facility Study stage, but facing regulatory headwind from Van Zandt County moratorium (Feb 2026) pausing green energy projects
Financing
Not recorded

Milestones in this assessment

WithdrawnFeb 2026Latest in this assessment

Van Zandt County moratorium passed pausing all planned green energy projects including lithium battery storage

ketk.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. ketk.com/news/local-news/vote-set-to-halt-lithium-battery-storage-construction/
  2. ketk.com/news/local-news/van-zandt-commissioners-pass-moratorium-pausing-lithium-storage/
  3. cleanview.co/power-projects/planned/battery-storage-projects/texas/23INR0464/sloan-storage
  4. renewablesinfo.org/project/ercot-23inr0464-sloan-storage

Commercial operation date: LBNL proposes 2026-03-27 COD. Cleanview aggregator confirms March 2026 expectation. No contradictory developer announcements found, but project faces local opposition via Van Zandt County moratorium (Feb 2026) which may delay timeline.

Developer: Only LBNL filing entity 'Sloan Energy Storage LLC' is available. No press releases, corporate announcements, or news coverage identify a parent operating company. Likely a project-specific SPV, but ultimate developer/owner remains unidentified in public sources.

Status: LBNL shows 'active' at Facility Study stage. However, Van Zandt County Commissioners passed a moratorium in Feb 2026 halting lithium battery storage construction, which may impact this Henderson County project if jurisdictional overlap or county-level opposition spreads.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Sloan Storage is a proposed 200.9 MW battery storage project located in Henderson County, Texas. The project, developed by Sloan Energy Storage LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0464, with a queue entry date of February 21, 2022. The proposed commercial operation date is March 27, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.

The Sloan Storage project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Henderson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Sloan Energy Storage LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

3179 Pauline 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Lake Pauline Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.