SAHARA BESS (SOHO BESS) (ERCOT-23INR0419) — Project Summary

Queue ID
ERCOT-23INR0419
Capacity
204.4 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
ESTX-PLD-HOUSTON2
IA Status
IA Executed

SAHARA BESS (SOHO BESS)

ERCOT-23INR0419BetaActiveBatteryERCOTLBNL

204.4 MW storage in Brazoria, TX · In queue since December 2021 · Proposed COD June 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

204.4 MW

Capacity

1

Components

Battery

4y 11m

In Queue

IA Executed

IA Phase

Signed Dec 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1 year

IA → COD

3y 6m

Total Duration

1 year

Schedule

6 months past proposed COD

Construction75%
Queue EntryDec 3, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 1, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-06-01

Queue history
23INR0419 · 55 monthly ERCOT reports, Dec 2021 – Jun 2026

Projected COD moved

5 times

Jan 2024 → Jun 2026

Net change

+29 months

first report to latest

Capacity

206 → 204 MW

changed in the reports

Latest stage

Commercial operation

last listed Jun 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 3, 2021
Facilities study approvedMay 2, 2025
Interconnection agreement signedDec 1, 2022
Approved for energizationJan 13, 2026
Approved for synchronizationFeb 20, 2026
Approved for commercial operationJul 23, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jun 1, 2026
From queue filing
Developer in saved assessment
Greenflash Infrastructure
Ownership change in saved research
Status at research time
IA Executed
IA Executed — financing secured October 2025, construction expected to commence 2026 toward June 2026 COD
Financing
Secured
Hybrid tax equity and debt financing closed October 2025 by Greenflash Infrastructure for 400MW/800MWh Project Soho (amount undisclosed)
Ownership history
  1. 2025-06·Prologis Energy (ESTX-PLD-HOUSTON2)→Greenflash Infrastructureenergy-storage.news

Milestones in this assessment

IA executedDec 2022

Interconnection Agreement executed with ERCOT

interconnection.fyi
Ownership changeJun 2025

Prologis Energy sold 400MW/800MWh BESS in Alvin, Texas to Greenflash Infrastructure

energy-storage.news
Financing closeOct 9, 2025

Greenflash closed hybrid tax capital and debt financing for Project Soho

energy-storage.news
COD targetJun 2026Latest in this assessment

Expected commercial operation date June 2026

cleanview.co
Research sources and reasoning (6 recorded sources)

high confidence at research time

  1. energy-storage.news/greenflash-infrastructure-secures-financing-for-texass-largest-standalone-bess/
  2. renewablesnow.com/news/greenflash-snatches-up-200-mw-battery-project-in-texas-1283254/
  3. energy-storage.news/prologis-energy-sells-400mw-800mwh-bess-in-exas/
  4. cleanview.co/power-projects/planned/battery-storage-projects/texas/69200_SOHO2/sahara-bess-soho-bess
  5. interconnection.fyi/project/ercot-23inr0419
  6. ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls

Commercial operation date: LBNL proposed COD of June 2026 is consistent with Texas PUC filing and ERCOT capacity charts. No contradictory signals from recent news; Greenflash financing announcement (Oct 2025) for 'Project Soho' suggests active development toward this timeline.

Developer: LBNL filing entity 'ESTX-PLD-HOUSTON2' is a Prologis Energy shell LLC. Prologis Energy sold the project to Greenflash Infrastructure in mid-2025 (announced June 2025, financing closed October 2025). Cleanview still lists 'Prologis' as developer, reflecting pre-sale data.

Status: LBNL status 'IA Executed' (Dec 2022) remains accurate for queue position. Greenflash closed hybrid tax equity and debt financing in October 2025, indicating project is moving from development to construction phase.

About

Saved background

Generated Apr 10, 2026 · Predates Jun 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The SOHO BESS project is a proposed 206.32 MW battery storage project located in Brazoria County, Texas. The developer is ESTX-PLDHOUSTON2. It is interconnected within the ERCOT region under queue ID ERCOT-23INR0419.

The project entered the ERCOT interconnection queue on December 3, 2021, with a proposed commercial operation date of June 1, 2026. The interconnection agreement (IA) for the project has been executed as of December 1, 2022. The point of interconnection (POI) is the 43035 Oasis 345kV location.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Jun 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

ESTX-PLD-HOUSTON2

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

43035 Oasis 345kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
MEDIUM
Nearest Node (Estimated)
COSTAL

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.