Bexar ESS
102.6 MW storage in Bexar, TX · In queue since September 2021 · Proposed COD December 2025
102.6 MW
Capacity
1
Components
Battery
5y 2m
In Queue
IA Executed
IA Phase
Signed Jul 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 10m
IA → COD
2y 5m
Total Duration
1y 10m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-12-31
Projected COD moved
10 times
Aug 2024 → Feb 2026
Net change
+18 months
first report to latest
Capacity
102 → 103 MW
changed in the reports
Latest stage
Commercial operation
last listed Feb 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
20-year PPA announced with CPS Energy for 120MW/480MWh Alamo City ESS project
newsroom.cpsenergy.comProject targeting 2027 commercial operation per groundbreaking announcement
en.sedaily.comResearch sources and reasoning (7 recorded sources)
high confidence at research time
- newsroom.cpsenergy.com/cps-energy-battery-storage/
- upi.com/Top_News/World-News/2026/05/20/OCI-holdings-texas-power-project/8841779282024/
- expressnews.com/business/article/cps-oci-battery-site-san-antonio-bexar-county-19964817.php
- bicmagazine.com/industry/tank-term-storage/oci-and-cps-energy-announce-battery-energy-storage-system-in-texas/
- en.sedaily.com/finance/2026/05/20/oci-holdings-breaks-ground-on-texas-ess-project-with-cps
- electrek.co/2024/12/06/battery-storage-project-will-boost-san-antonio-grid/
- power-technology.com/news/oci-energy-cps-energy/
Commercial operation date: LBNL proposed COD was 2025-12-31, but May 2026 groundbreaking announcement from OCI Holdings states the project targets 2027 commercial operation. This is consistent with typical 12-18 month construction timeline for battery storage.
Developer: LBNL filing entity is 'Bexar ESS LLC' (project shell), but all press releases and news coverage identify OCI Energy (U.S. subsidiary of South Korea's OCI Holdings) as the actual developer and operator.
Status: LBNL shows 'Active' with IA executed July 2023. May 2026 groundbreaking announcements from OCI Holdings and multiple news sources confirm construction has commenced.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Bexar ESS project is a proposed 102.6 MW battery storage project located in Bexar County, Texas. Developed by Bexar ESS LLC, the project consists entirely of battery storage. It is interconnected within the ERCOT region under queue ID ERCOT-23INR0381, with an interconnection queue entry date of September 21, 2021. The proposed commercial operation date is February 10, 2026, and the Interconnection Agreement was executed on July 31, 2023.
The project is linked to the existing Bexar ESS operating plant (EIA plant ID 66400). The Bexar ESS project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Feb 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bexar ESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5007 Alamo One 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- RN_OCI_ALAMO
- POI Substation
- OCI Alamo 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26