Fewell Solar
203.5 MW generation in Limestone, TX · In queue since August 2021 · Proposed COD May 2028
203.5 MW
Capacity
1
Components
Solar
5y 3m
In Queue
IA Executed
IA Phase
Signed Aug 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 years
IA → COD
4y 9m
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-15
Projected COD moved
5 times
Dec 2023 → May 2028
Net change
+53 months
first report to latest
Capacity
204 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Texas Chapter 313 tax abatement agreement with Groesbeck ISD for $192M qualified investment
comptroller.texas.govInterconnection agreement executed between Oncor and Fewell Solar LLC
interchange.puc.texas.govResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- comptroller.texas.gov/economy/development/prop-tax/ch313/agreement-docs-details.php?id=1830
- s3.amazonaws.com/scschoolfiles/546/groesbeck_isd_-_04252022_-_bt_fewell_presentation.pdf
- interchange.puc.texas.gov/Search/Filings?ControlNumber=35077
- ercotqueue.com/project/23INR0367
- ercot.com/files/docs/2024/12/05/mora_february2025.xlsx
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-03-15. No contradicting news or press releases found; ERCOT Monthly Outlook (Dec 2024) lists project for 2027 with 0 MW online, consistent with LBNL target.
Developer: LBNL filing entity is 'Fewell Solar LLC' (project shell). Texas Comptroller Ch313 documents and Groesbeck ISD presentation identify 'BT Fewell Solar, LLC' developed by Belltown Power as the operating parent company.
Status: LBNL shows 'active' status with IA executed 2023-08-18. PUC Interchange confirms interconnection agreement filing Sept 2023. No construction or withdrawal announcements found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Fewell Solar is a proposed 203.5 MW solar generation project located in Limestone County, Texas. The project, developed by Fewell Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0367. It entered the queue on August 19, 2021, with a proposed commercial operation date of March 15, 2027.
The project's Interconnection Agreement (IA) was executed on August 18, 2023. The point of interconnection is Tap 138kV 3597 Groesbeck - 3634 Groesbeck Main. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Limestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Fewell Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3597 Groesbeck - 3634 Groesbeck Main
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DIVR_SLR_RN
- POI Substation
- Groesbeck Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Fewell Solar
Data-driven briefing on Fewell Solar — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.