Tierra Seca BESS (ERCOT-23INR0364) — Project Summary

Queue ID
ERCOT-23INR0364
Capacity
102.7 MW
Technology
Battery
Status
active
Location
Val Verde, TX
Region
ERCOT
Developer
Tierra Seca BESS LLC
IA Status
IA Executed

Tierra Seca BESS

ERCOT-23INR0364BetaActiveBatteryERCOTLBNL

102.7 MW storage in Val Verde, TX · In queue since August 2021 · Proposed COD January 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

102.7 MW

Capacity

1

Components

Battery

5y 3m

In Queue

IA Executed

IA Phase

Signed May 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 9m

IA → COD

2y 8m

Total Duration

1y 9m

Schedule

10 months past proposed COD

Construction75%
Queue EntryAug 24, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 18, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-01-29

Queue history
23INR0364 · 53 monthly ERCOT reports, Sep 2021 – Jan 2026

Projected COD moved

9 times

Jun 2023 → Jan 2026

Net change

+31 months

first report to latest

Capacity

101 → 103 MW

changed in the reports

Latest stage

Commercial operation

last listed Jan 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 24, 2021
Facilities study approvedOct 21, 2024
Interconnection agreement signedMay 18, 2023
Approved for energizationOct 27, 2025
Approved for synchronizationNov 4, 2025
Approved for commercial operationFeb 4, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
May 12, 2026
Differs from queue: Jan 29, 2026
Developer in saved assessment
Spearmint Energy
Filed as Tierra Seca BESS LLC
Status at research time
Online
Online — COD confirmed May 12, 2026 per Renewables Now; interconnection.fyi also lists as operational
Financing
Secured
$252 million financing closed April 2025, led by undisclosed lenders, advised by Paul Hastings for Tierra Seca and Seven Flags BESS pair

Milestones in this assessment

IA executedMay 18, 2023

Interconnection Agreement executed with ERCOT

interchange.puc.texas.gov
Financing closeApr 2025

$252M financing closed for Tierra Seca and Seven Flags BESS projects

paulhastings.com
COD targetMay 12, 2026Latest in this assessment

Commercial operation date confirmed for 100MW/200MWh Tierra Seca BESS in Del Rio

renewablesnow.com
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. energy-storage.news/spearmint-energy-secures-us250-million-for-two-texas-bess-totalling-400mwh/
  2. paulhastings.com/news/paul-hastings-advises-spearmint-on-usd252-million-battery-energy-storage-systems-financing
  3. renewablesnow.com/news/spearmint-confirms-cod-for-400-mwh-texas-battery-duo-1294588/
  4. interconnection.fyi/project/ercot-23inr0364
  5. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending

Commercial operation date: Renewables Now article dated May 12, 2026 confirms COD for Tierra Seca BESS, stating 'Spearmint confirms COD for 400-MWh Texas battery duo.' This is 3.5 months later than LBNL's proposed 2026-01-29 date, representing typical construction schedule adjustment.

Developer: LBNL filing uses project LLC 'Tierra Seca BESS LLC'. Multiple 2025 sources (Energy-Storage.News, Paul Hastings, Del Rio Chamber) confirm Spearmint Energy as the operating company and developer. Paul Hastings press release explicitly names 'Spearmint' as client for $252M financing.

Status: LBNL shows 'active' with IA executed 2023-05-18. Renewables Now May 2026 article confirms commercial operation achieved. Interconnection.fyi database also lists project as 'currently operational.'

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Tierra Seca BESS is a proposed 102.7 MW battery storage project in Val Verde County, Texas. Developed by Tierra Seca BESS LLC, the project entered the ERCOT interconnection queue as queue ID ERCOT-23INR0364 on August 24, 2021, with a proposed commercial operation date of October 1, 2025. The project has an Interconnection Agreement (IA) executed on May 18, 2023.

The proposed project is linked to the existing Tierra Seca operating plant (EIA plant ID 68748). Recent news coverage has discussed the development.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Jan 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Val Verde

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Tierra Seca BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

138kV 8255 HAMILTON4A (Hamilton Road Substation)

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
HAMI_BESS_RN
POI Substation
Del Rio Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.