Tierra Seca BESS
102.7 MW storage in Val Verde, TX · In queue since August 2021 · Proposed COD January 2026
102.7 MW
Capacity
1
Components
Battery
5y 3m
In Queue
IA Executed
IA Phase
Signed May 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 9m
IA → COD
2y 8m
Total Duration
1y 9m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-01-29
Projected COD moved
9 times
Jun 2023 → Jan 2026
Net change
+31 months
first report to latest
Capacity
101 → 103 MW
changed in the reports
Latest stage
Commercial operation
last listed Jan 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
$252M financing closed for Tierra Seca and Seven Flags BESS projects
paulhastings.comCommercial operation date confirmed for 100MW/200MWh Tierra Seca BESS in Del Rio
renewablesnow.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- energy-storage.news/spearmint-energy-secures-us250-million-for-two-texas-bess-totalling-400mwh/
- paulhastings.com/news/paul-hastings-advises-spearmint-on-usd252-million-battery-energy-storage-systems-financing
- renewablesnow.com/news/spearmint-confirms-cod-for-400-mwh-texas-battery-duo-1294588/
- interconnection.fyi/project/ercot-23inr0364
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
Commercial operation date: Renewables Now article dated May 12, 2026 confirms COD for Tierra Seca BESS, stating 'Spearmint confirms COD for 400-MWh Texas battery duo.' This is 3.5 months later than LBNL's proposed 2026-01-29 date, representing typical construction schedule adjustment.
Developer: LBNL filing uses project LLC 'Tierra Seca BESS LLC'. Multiple 2025 sources (Energy-Storage.News, Paul Hastings, Del Rio Chamber) confirm Spearmint Energy as the operating company and developer. Paul Hastings press release explicitly names 'Spearmint' as client for $252M financing.
Status: LBNL shows 'active' with IA executed 2023-05-18. Renewables Now May 2026 article confirms commercial operation achieved. Interconnection.fyi database also lists project as 'currently operational.'
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Tierra Seca BESS is a proposed 102.7 MW battery storage project in Val Verde County, Texas. Developed by Tierra Seca BESS LLC, the project entered the ERCOT interconnection queue as queue ID ERCOT-23INR0364 on August 24, 2021, with a proposed commercial operation date of October 1, 2025. The project has an Interconnection Agreement (IA) executed on May 18, 2023.
The proposed project is linked to the existing Tierra Seca operating plant (EIA plant ID 68748). Recent news coverage has discussed the development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jan 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Val Verde
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tierra Seca BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV 8255 HAMILTON4A (Hamilton Road Substation)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HAMI_BESS_RN
- POI Substation
- Del Rio Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.