Bordertown BESS
100 MW storage in Starr, TX · In queue since August 2021 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
5y 3m
In Queue
—
IA Status
Signed Oct 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 2m
IA → COD
6y 2m
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-12-01
Projected COD moved
7 times
Jun 2023 → Dec 2028
Net change
+66 months
first report to latest
Capacity
106 → 100 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2022-06·Black Mountain Energy Storage→Recurrent Energyenergy-storage.news
Milestones in this assessment
Black Mountain Energy Storage sold Bordertown BESS and Fort Duncan BESS (400MWh total) to Recurrent Energy
energy-storage.newsERCOT Standard Generation Interconnection Agreement executed between AEP Texas Inc. and Bordertown BESS LLC
interchange.puc.texas.govPreliminary plat approved for Bordertown BESS Subdivision for battery energy storage facility
cdn.prod.website-files.comERCOT capacity planning documents list 2026 expected online date
ercot.comResearch sources and reasoning (7 recorded sources)
high confidence at research time
- energy-storage.news/canadian-solar-subsidiary-recurrent-buys-400mwh-standalone-storage-projects-in-ercot/
- bmenergystorage.com/news/black-mountain-sells-two-texas-standalone-storage-projects/
- cdn.prod.website-files.com/64da3765f9dc556c39e2a301/674de907ee257067003da120_PZ_MEMO_12.2.24.pdf
- ercot.com/files/docs/2025/03/07/CapacityChangesbyFuelTypeCharts_February_2025.xlsx
- ercot.com/files/docs/2025/07/07/MORA_September2025.pdf
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- energy-storage.news/nadbank-says-recurrent-energy-texas-bess-carries-acceptable-risk-for-construction-loan/
Commercial operation date: ERCOT's July 2025 MORA report lists Bordertown BESS with a 2026 expected online date, and the February 2025 capacity changes spreadsheet also shows 2026. This is 2 years earlier than LBNL's 2028-12-01 filing date, reflecting updated project timeline.
Developer: LBNL filing entity is 'Bordertown BESS LLC' (shell LLC). Black Mountain Energy Storage originally developed the project but sold it to Recurrent Energy (Canadian Solar subsidiary) in June 2022, confirmed by multiple sources including Energy-Storage.News and Black Mountain's own announcement.
Status: LBNL status is 'active' which aligns with ground reality. December 2024 preliminary plat filing for subdivision shows active permitting progress, and ERCOT's 2025 reports consistently list 2026 as expected online date.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Bordertown BESS project is a proposed 100 MW battery storage project located in Starr County, Texas. Developed by Bordertown BESS LLC, the project entered the ERCOT interconnection queue as ERCOT-23INR0354 on September 1, 2021. The project's proposed commercial operation date is June 15, 2027.
The Bordertown BESS project has an Interconnection Agreement (IA) executed on October 12, 2022. The point of interconnection is the 8796 Roma 138kV. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Starr
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.