Seven Flags BESS (ERCOT-23INR0351) — Project Summary

Queue ID
ERCOT-23INR0351
Capacity
102.7 MW
Technology
Battery
Status
active
Location
Webb, TX
Region
ERCOT
Developer
Seven Flags BESS LLC
IA Status
IA Executed

Seven Flags BESS

ERCOT-23INR0351BetaActiveBatteryERCOTLBNL

102.7 MW storage in Webb, TX · In queue since September 2021 · Proposed COD January 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

102.7 MW

Capacity

1

Components

Battery

5y 2m

In Queue

IA Executed

IA Phase

Signed May 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 8m

IA → COD

2y 8m

Total Duration

1y 8m

Schedule

11 months past proposed COD

Construction75%
Queue EntrySep 1, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 19, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-01-07

Queue history
23INR0351 · 53 monthly ERCOT reports, Sep 2021 – Jan 2026

Projected COD moved

13 times

Jun 2023 → Jan 2026

Net change

+31 months

first report to latest

Capacity

106 → 103 MW

changed in the reports

Latest stage

Commercial operation

last listed Jan 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 1, 2021
Facilities study approvedDec 19, 2024
Interconnection agreement signedMay 19, 2023
Approved for energizationSep 22, 2025
Approved for synchronizationSep 30, 2025
Approved for commercial operationFeb 13, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
2026
Developer in saved assessment
Spearmint Energy
Filed as Seven Flags BESS LLC
Status at research time
Active
Active — construction financed and underway, targeting 2026 COD per April 2025 financing close
Financing
Secured
$252 million construction financing closed April 2025, part of broader $250M package for two Texas BESS projects (Seven Flags + Tierra Seca)

Milestones in this assessment

IA executedMay 19, 2023

Interconnection Agreement executed with AEP Texas

paulhastings.com
Financing closeApr 2025

$252M construction financing closed for 100MW/200MWh Seven Flags BESS in Laredo

paulhastings.com
COD target2026Latest in this assessment

Project reported operational in 2026

cleanview.co
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. paulhastings.com/news/paul-hastings-advises-spearmint-on-usd252-million-battery-energy-storage-systems-financing
  2. cleanview.co/power-projects/operating/battery-storage-projects/texas/66689/seven-flags-bess-llc
  3. energy-storage.news/spearmint-energy-secures-us250-million-for-two-texas-bess-totalling-400mwh/
  4. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending

Commercial operation date: LBNL proposed COD of 2026-01-07 aligns with Cleanview reporting the project became operational in 2026, and Paul Hastings April 2025 financing announcement for construction supports a 2026 timeline.

Developer: Paul Hastings press release (April 2025) explicitly identifies Spearmint Energy as the developer securing $252M financing for Seven Flags BESS, while LBNL filing uses the project-LLC 'Seven Flags BESS LLC'.

Status: LBNL status 'active' with IA executed (May 2023) is accurate. April 2025 financing close for $252M indicates construction phase, consistent with 2026 COD target.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Seven Flags BESS is a proposed 102.7 MW battery storage project located in Webb County, Texas. The project, developed by Seven Flags BESS LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0351. It entered the queue on September 1, 2021, with a proposed commercial operation date of December 15, 2025. The interconnection agreement was executed on May 19, 2023.

The development project is linked to the existing operating plant Seven Flags BESS LLC (EIA plant ID 66689). The project has been featured in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Jan 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Webb

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Seven Flags BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

8295 Wormser Substation 138kV

Data Source

LBNL

DeveloperBlack Mountain Energy StorageEnergy-Storage.News · 2022-07-26
TransactionAcquisitionEnergy-Storage.News · 2022-07-26
OfftakerCypress Creek RenewablesEnergy-Storage.News · 2022-07-26
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
POI Substation
Wormser Road Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-03-14

View all articles

No Ask reports yet for this entity.

Ask about Seven Flags BESS
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.