Elmax Power Station (ERCOT-23INR0345) — Project Summary

Queue ID
ERCOT-23INR0345
Capacity
518.83 MW
Technology
Gas
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Elmax Generating, LLC
IA Status
IA Executed

Elmax Power Station

ERCOT-23INR0345BetaActiveGasERCOTLBNL

518.83 MW generation in Harris, TX · In queue since September 2021 · Proposed COD July 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

518.83 MW

Capacity

1

Components

Gas

5y 2m

In Queue

IA Executed

IA Phase

Signed Feb 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 5m

IA → COD

3y 5m

Total Duration

3y 5m

Construction75%
Queue EntrySep 14, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 3, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2028-07-05

Queue history
23INR0345 · 55 monthly ERCOT reports, Sep 2021 – Mar 2026

Projected COD moved

4 times

Jun 2024 → Jul 2028

Net change

+49 months

first report to latest

Capacity

510 → 519 MW

changed in the reports

Latest stage

Cancelled

last listed Mar 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 14, 2021
Facilities study approvedMar 29, 2024
Interconnection agreement signedFeb 3, 2025
CancelledApr 1, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jul 5, 2028
From queue filing
Developer in saved assessment
WattBridge Energy LLC
Filed as Elmax Generating, LLC
Status at research time
IA Executed
Active in the ERCOT queue with an interconnection agreement executed (Feb 2025). No evidence of construction start or financing close. One aggregator (interconnection.fyi) snippet says 'withdrawn', but LBNL and interxdata show active.
Financing
Not recorded

Milestones in this assessment

IA executedFeb 3, 2025Latest in this assessment

ERCOT Standard Generation Interconnection Agreement with Elmax Generating, LLC for Elmax Power Station filed at the PUC. The date comes from the LBNL IA record, not the filing snippet.

interchange.puc.texas.gov
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. us-east-1.storage.xata.sh/m70jvtdh6578mv0p12pfh5phcv8ngro0
  2. us-east-1.storage.xata.sh/m70jvtsjpnhoejvp3er9adodks9psq9s
  3. interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2058
  4. interxdata.com/projects/elmax-power-station-ercot-23inr0345/
  5. interconnection.fyi/project/ercot-23inr0345

Commercial operation date: No search result gives a COD or construction timeline for Elmax. The only date is the LBNL proposed COD of 2028-07-05, which is consistent with an IA executed in Feb 2025.

Developer: A TCEQ standard permit technical review says 'WattBridge Energy LLC is proposing to build and operate the Elmax Power Station', while a second review and the PUC SGIA filing name Elmax Generating, LLC as owner and counterparty. This suggests Elmax Generating is the project LLC and WattBridge the operating developer, but no source states the relationship outright and neither document is dated.

Status: LBNL lists status active with IA executed 2025-02-03, and a PUC Interchange filing of the ERCOT Standard Generation Interconnection Agreement for Elmax Power Station supports this. The 'withdrawn' snippet from interconnection.fyi conflicts and is unverified, so it is flagged but not adopted.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Elmax Power Station (TEF- Due Diligence) is a proposed project in Harris County, Texas, being developed by Elmax Generating, LLC. This gas-fired generation project has a total capacity of 518.83 MW. The project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0345, with a queue entry date of September 14, 2021.

The proposed commercial operation date for the Elmax Power Station is July 5, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138 kV Lake Houston (#40820) - Atascocita (#40130) ckt 66.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Mar 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Elmax Generating, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138 kV Lake Houston (#40820) - Atascocita (#40130) ckt 66

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.