Larkspur Energy Storage (ERCOT-23INR0340) — Project Summary

Queue ID
ERCOT-23INR0340
Capacity
307.46 MW
Technology
Battery
Status
active
Location
Upton, TX
Region
ERCOT
Developer
Larkspur Energy Storage LLC
IA Status
IA Executed

Larkspur Energy Storage

ERCOT-23INR0340BetaActiveBatteryERCOTLBNL

307.46 MW storage in Upton, TX · In queue since August 2021 · Proposed COD May 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

307.46 MW

Capacity

1

Components

Battery

5y 3m

In Queue

IA Executed

IA Phase

Signed Feb 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

6 months

IA → COD

5y 3m

Total Duration

6 months

Construction75%
Queue EntryAug 2, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 28, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-05-05

Queue history
23INR0340 · 57 monthly ERCOT reports, Aug 2021 – Apr 2026

Projected COD moved

4 times

Mar 2023 → May 2027

Net change

+50 months

first report to latest

Capacity

307 MW

unchanged in the reports

Latest stage

Cancelled

last listed Apr 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 2, 2021
Interconnection agreement signedFeb 28, 2022
CancelledMay 19, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
May 5, 2027
From queue filing
Developer in saved assessment
Larkspur Energy Storage LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue with IA executed (2022-02-28). Not operational. No construction start or financing announcement found. One aggregator snippet (interconnection.fyi) says 'withdrawn', which conflicts with the other sources.
Financing
Not recorded

Milestones in this assessment

COD targetMay 4, 2027Latest in this assessment

ERCOT queue proposed completion date pushed from May 4, 2026 to May 4, 2027 (reported Apr 2025).

newsletter.interconnection.fyi
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. newsletter.interconnection.fyi/p/interconnection-weekly-project-updates-ad5
  2. ercotqueue.com/developer/larkspur-energy-storage-llc
  3. interconnection.fyi/project/ercot-23inr0340

Commercial operation date: LBNL lists a proposed COD of 2027-05-05. The interconnection.fyi newsletter (Apr 2025) reports the ERCOT date moved from May 4, 2026 to May 4, 2027, which matches LBNL within a day. That newsletter draws on the same queue data, so it is not independent confirmation. No developer press release or news article gives a financing-backed COD.

Developer: Only the project LLC appears in the LBNL filing, ercotqueue.com and the PUC Texas filings. No parent or operating company was identified in any source, so a shell-vs-parent determination is not possible.

Status: LBNL shows active with an executed IA. ercotqueue.com lists 1 active, 0 dropped, and the April 2025 ERCOT update shows a COD revision to 2027, which implies the project was still live. The interconnection.fyi 'withdrawn' snippet is truncated and unconfirmed, so it is treated as a possible stale or erroneous flag.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Larkspur Energy Storage is a proposed 307.46 MW battery storage project located in Upton County, Texas. The project, developed by Larkspur Energy Storage LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0340, with a queue entry date of August 2, 2021. The proposed commercial operation date is May 5, 2027.

The project has an executed Interconnection Agreement (IA), dated February 28, 2022. The point of interconnection (POI) is the 71213 Benedum 138kV substation. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Apr 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Upton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Larkspur Energy Storage LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

71213 Benedum 138kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.