Hofbrau BESS
180.72 MW storage in Tom Green, TX · In queue since September 2021 · Proposed COD July 2028
180.72 MW
Capacity
1
Components
Battery
5y 2m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Projected COD moved
3 times
Oct 2023 → Jul 2028
Net change
+57 months
first report to latest
Capacity
180 → 181 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Original proposed completion date before revision to June 2028
interconnectionfyi.substack.comRevised proposed completion date per Jan 2025 interconnection update
interconnectionfyi.substack.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- ercotqueue.com/project/23INR0312
- ercotqueue.com/developer/momentum-hofbrau-llc
Commercial operation date: LBNL queue shows July 1, 2028 COD. Interconnection.fyi newsletter (Jan 2025) notes the proposed completion changed from May 2026 to June 2028, confirming the 2028 target is current. No developer press releases or financing announcements found to contradict this date.
Developer: LBNL filing entity is 'Momentum Hofbrau LLC' (project-specific shell). AWS/Modo ERCOT buildout report (May 2024) lists parent as 'Momentum Energy Storage Partners, LLC', the operating company behind the project vehicle.
Status: LBNL shows 'active' status at Facility Study stage with no IA date. Multiple tracking sources confirm project remains in queue without withdrawal, but ercotqueue.com flags low build chance given stage stagnation.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Hofbrau BESS project is a proposed 180.72 MW battery storage project located in Tom Green County, Texas. Developed by Momentum Hofbrau LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0312, with a queue entry date of September 22, 2021.
The proposed commercial operation date for the Hofbrau BESS project is July 1, 2028. The project's interconnection status is currently in the Facility Study phase. Recent news coverage has discussed the development project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Momentum Hofbrau LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6442 Redcreek 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.