Hofbrau BESS (ERCOT-23INR0312) — Project Summary

Queue ID
ERCOT-23INR0312
Capacity
180.72 MW
Technology
Battery
Status
active
Location
Tom Green, TX
Region
ERCOT
Developer
Momentum Hofbrau LLC
IA Status
Facility Study

Hofbrau BESS

ERCOT-23INR0312BetaActiveBatteryERCOTLBNL + Live

180.72 MW storage in Tom Green, TX · In queue since September 2021 · Proposed COD July 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

180.72 MW

Capacity

1

Components

Battery

5y 2m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 10m

Facilities Study50%
Queue EntrySep 22, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-01

Queue history
23INR0312 · 61 monthly ERCOT reports, Sep 2021 – Sep 2026

Projected COD moved

3 times

Oct 2023 → Jul 2028

Net change

+57 months

first report to latest

Capacity

180 → 181 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 22, 2021

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jul 1, 2028
From queue filing
Developer in saved assessment
Momentum Energy Storage Partners
Filed as Momentum Hofbrau LLC
Status at research time
Active
Active — Facility Study stage, no IA executed. Build probability estimated at 5% by ercotqueue.com due to lack of interconnection agreement progress.
Financing
Not recorded

Milestones in this assessment

COD targetMay 2026

Original proposed completion date before revision to June 2028

interconnectionfyi.substack.com
COD targetJun 2028Latest in this assessment

Revised proposed completion date per Jan 2025 interconnection update

interconnectionfyi.substack.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
  2. modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
  3. ercotqueue.com/project/23INR0312
  4. ercotqueue.com/developer/momentum-hofbrau-llc

Commercial operation date: LBNL queue shows July 1, 2028 COD. Interconnection.fyi newsletter (Jan 2025) notes the proposed completion changed from May 2026 to June 2028, confirming the 2028 target is current. No developer press releases or financing announcements found to contradict this date.

Developer: LBNL filing entity is 'Momentum Hofbrau LLC' (project-specific shell). AWS/Modo ERCOT buildout report (May 2024) lists parent as 'Momentum Energy Storage Partners, LLC', the operating company behind the project vehicle.

Status: LBNL shows 'active' status at Facility Study stage with no IA date. Multiple tracking sources confirm project remains in queue without withdrawal, but ercotqueue.com flags low build chance given stage stagnation.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Hofbrau BESS project is a proposed 180.72 MW battery storage project located in Tom Green County, Texas. Developed by Momentum Hofbrau LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0312, with a queue entry date of September 22, 2021.

The proposed commercial operation date for the Hofbrau BESS project is July 1, 2028. The project's interconnection status is currently in the Facility Study phase. Recent news coverage has discussed the development project.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Tom Green

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Momentum Hofbrau LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

6442 Redcreek 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.