Greater Bryant G Solar
17.7 MW generation in Midland, TX · In queue since June 2021 · Proposed COD November 2026
17.7 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Phase
Signed Jul 2022
Queue → IA
1y 1m
IA → COD
4y 4m
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-11-16
The Greater Bryant G Solar project is a proposed 17.7 MW solar generation project located in Midland County, Texas. The developer is Greater Bryant G Solar, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0300, with a queue entry date of June 17, 2021. The project's proposed commercial operation date is November 16, 2026, and an Interconnection Agreement was executed on July 18, 2022.
The point of interconnection is the 11165 Sloan Switch 138kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Midland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greater Bryant G Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11165 Sloan Switch 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.