BRP Aras BESS (ERCOT-23INR0272) — Project Summary

Queue ID
ERCOT-23INR0272
Capacity
303.59 MW
Technology
Battery
Status
active
Location
Upton, TX
Region
ERCOT
Developer
BRP Aras BESS LLC
IA Status
Facility Study

BRP Aras BESS

ERCOT-23INR0272BetaActiveBatteryERCOTLBNL

303.59 MW storage in Upton, TX · In queue since May 2021 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

303.59 MW

Capacity

1

Components

Battery

5y 6m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

7y 7m

Facilities Study50%
Queue EntryMay 31, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Queue history
23INR0272 · 59 monthly ERCOT reports, May 2021 – Mar 2026

Projected COD moved

3 times

Oct 2023 → Dec 2028

Net change

+62 months

first report to latest

Capacity

304 MW

unchanged in the reports

Latest stage

Cancelled

last listed Mar 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 31, 2021
CancelledApr 8, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 1, 2028
From queue filing
Developer in saved assessment
BRP Aras BESS LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at Facility Study stage with no IA executed. One aggregator (interconnection.fyi) lists it as withdrawn, which conflicts with LBNL and other trackers.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-23inr0272
  2. interxdata.com/projects/brp-aras-bess-ercot-23inr0272/
  3. ercotqueue.com/developer/brp-aras-bess-llc
  4. energy-storage.news/gridstor-acquires-150mw-300mwh-texas-bess-from-brp/
  5. renewablesnow.com/news/gridstor-buys-150-mw300-mwh-battery-project-in-texas-1270261/

Commercial operation date: Only the LBNL proposed COD (2028-12-01) exists. interconnection.fyi shows Nov 30, 2028, which is the same ERCOT-derived date and not independent. No developer press release or news article gives a financing-backed COD for this project.

Developer: Every source names BRP Aras BESS LLC as the owner. The 'BRP' prefix may point to Balanced Rock Power, which sold a 150MW/300MWh Texas BESS to GridStor. The snippets don't name that project, and 150 MW doesn't match this 303.59 MW project, so I did not link them or record an ownership change.

Status: LBNL and ercotqueue.com show the project as active. interxdata, whose page is dated Jul 2026, also shows it active. The single 'withdrawn' listing is unconfirmed and may reflect a different data pull, so LBNL's status is kept.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The BRP Aras BESS project is a proposed 303.59 MW battery storage project located in Upton County, Texas. The developer is BRP Aras BESS LLC. It is interconnected to the ERCOT grid under queue ID ERCOT-23INR0272, with a queue entry date of May 31, 2021. The proposed commercial operation date is December 1, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 76595 North McCamey 138kV location. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Mar 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Upton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Aras BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

76595 North McCamey 138kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
North McCamey Subsation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.