Limewood Solar (ERCOT-23INR0249) — Project Summary

Queue ID
ERCOT-23INR0249
Capacity
204.6 MW
Technology
Solar+Battery
Status
active
Location
Bell, TX
Region
ERCOT
Developer
Limewood Bell Renewables LLC
IA Status
IA Executed

Limewood Solar

ERCOT-23INR0249BetaActiveSolarBatteryERCOTLBNL + Live

204.6 MW hybrid in Bell, TX · In queue since April 2021 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

204.6 MW

Capacity

1

Components

Solar

5y 7m

In Queue

IA Executed

IA Phase

Signed Feb 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 10m

IA → COD

3y 10m

Total Duration

1y 10m

Construction75%
Queue EntryApr 30, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 22, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-29

Queue history
23INR0249 · 60 monthly ERCOT reports, Oct 2021 – Sep 2026

Projected COD moved

4 times

Jun 2023 → Dec 2026

Net change

+42 months

first report to latest

Capacity

204 → 205 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedApr 30, 2021
Facilities study approvedMar 14, 2025
Interconnection agreement signedFeb 22, 2023
Approved for energizationAug 10, 2026
Approved for synchronizationSep 15, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2026
From queue filing
Developer in saved assessment
Pine Gate Renewables
Filed as Limewood Bell Renewables LLC
Status at research time
Active
Active — construction began late 2024, project company filed Chapter 11 bankruptcy November 2025 amid policy uncertainty
Financing
In progress
Project represents $268M investment; Chapter 11 filing November 2025 suggests financing complications despite Meta offtake agreement signed May 2024

Milestones in this assessment

IA executedFeb 22, 2023

Interconnection Agreement executed with ERCOT

pv-tech.org
Groundbreaking2024

Construction began late 2024

x.com
Financing closeMay 2024

Environmental Asset Purchase Agreement signed with Meta for 204MW offtake

pv-tech.org
WithdrawnNov 2025Latest in this assessment

Limewood Bell Renewables LLC filed Chapter 11 bankruptcy amid policy uncertainty

x.com
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. pv-tech.org/pine-gate-meta-in-204mw-texas-solar-agreement/
  2. solarpowerworldonline.com/2024/05/pine-gate-meta-204-mw-solar/
  3. pinegaterenewables.com/limewood/
  4. pinegaterenewables.com/wp-content/uploads/2024/03/Limewood-Fact-Sheet-March-2024.pdf
  5. x.com/_RKConsultants/status/1986564131894264073

Commercial operation date: LBNL proposed COD of 2026-03-02 is the only explicit date available. Construction began late 2024 per bankruptcy filing, making 2026 plausible but no independent confirmation of specific target date exists.

Developer: LBNL filing entity is 'Limewood Bell Renewables LLC' (project shell). Multiple 2024-2025 sources confirm Pine Gate Renewables as the actual developer and owner-operator, with Meta as offtaker.

Status: LBNL shows IA Executed (2023-02-22) and Active status. Construction commenced late 2024 per bankruptcy filing. November 2025 Chapter 11 filing indicates financial distress but project remains in queue.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Limewood Solar is a proposed 204.6 MW solar generation project located in Bell County, Texas. The developer is Limewood Bell Renewables LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-23INR0249, with an interconnection queue entry date of April 30, 2021. The proposed commercial operation date is March 2, 2026.

The project's Interconnection Agreement (IA) has been executed as of February 22, 2023. Limewood Solar is linked to the existing Limewood Bell Renewables Solar operating plant (EIA plant ID 68853). The point of interconnection is the 3420 Temple Pecan Creek 138kV. The project has appeared in recent news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Bell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Limewood Bell Renewables LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

3420 Temple Pecan Creek 138kV

Data Source

LBNL + Live

DeveloperPine Gate RenewablesSolar Power World · 2025-08-05
TransactionPPASolar Power World · 2025-08-05
OfftakerMetaSolar Power World · 2025-08-05
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
LIME_SLR_UNIT1
POI Substation
Temple Pecan Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.