Tiger Solar
250.9 MW generation in Jones, TX · In queue since April 2021 · Proposed COD February 2027
250.9 MW
Capacity
1
Components
Solar
5y 7m
In Queue
IA Executed
IA Phase
Signed Oct 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 6m
IA → COD
2y 4m
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-02-26
Projected COD moved
4 times
Dec 2023 → Feb 2027
Net change
+38 months
first report to latest
Capacity
306 → 251 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT
lbnl_queue_snapshotResearch sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: Only LBNL queue data provides a COD target of 2027-06-30. No news or research findings discuss this specific ERCOT utility-scale project's timeline.
Developer: LBNL lists 'Vaca Del Sol, LLC' as developer. Search results only returned unrelated 'Tiger Solar' entities (a Virginia/Michigan residential solar installer). No evidence connects the residential company to this 250.9 MW ERCOT utility-scale project.
Status: LBNL shows 'active' status with IA executed 2024-10-30. No news coverage of construction start or project updates found in search results.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Tiger Solar is a proposed 255 MW solar generation project located in Jones County, Texas. Developed by Vaca Del Sol, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0244, with an interconnection queue entry date of April 29, 2021. The proposed commercial operation date is June 30, 2027, and the Interconnection Agreement (IA) was executed on October 30, 2024. The point of interconnection is the 68004 PHANTOM HILL 345KV substation.
The proposed project is linked to the existing, operating Tiger Solar facility (EIA plant ID 67357). Recent news coverage has highlighted the project, with articles focusing on industry and development aspects.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Vaca Del Sol, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68004 PHANTOM HILL 345KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANSON1_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesSolar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Tiger Solar
Data-driven briefing on Tiger Solar — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.