Venus Mill Storage (ERCOT-23INR0216) — Project Summary

Queue ID
ERCOT-23INR0216
Capacity
100.8 MW
Technology
Battery
Status
active
Location
Ellis, TX
Region
ERCOT
Developer
—
IA Status
—

Venus Mill Storage

ERCOT-23INR0216BetaActiveBatteryERCOTLBNL + Live

100.8 MW storage in Ellis, TX · In queue since March 2022 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

100.8 MW

Capacity

1

Components

Battery

4y 8m

In Queue

—

IA Status

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 9m

Pre-Study0%
Queue EntryMar 13, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Queue history
23INR0216 · 49 monthly ERCOT reports, Mar 2022 – Sep 2026

Projected COD moved

3 times

Jul 2024 → Dec 2027

Net change

+41 months

first report to latest

Capacity

104 → 101 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 14, 2022
Interconnection agreement signedDec 24, 2025
On ERCOT's inactive listMay 2022 – Jan 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 31, 2027
From queue filing
Developer in saved assessment
Key Capture Energy
Filed as AIH Texas Acquisitions, LLC
Status at research time
Active
Active — IA executed with Oncor in January 2026, project advancing toward construction
Financing
Not recorded

Milestones in this assessment

IA executedJan 23, 2026

Standard Generation Interconnection Agreement executed between Oncor and AIH Texas Acquisitions, LLC

interchange.puc.texas.gov
IA executedJan 27, 2026Latest in this assessment

Key Capture Energy announced signing of interconnection agreement with Oncor for 107.3 MW Venus Mill Storage

cleanview.co
Research sources and reasoning (3 recorded sources)

high confidence at research time

  1. cleanview.co/news/battery/key-capture-energy-signs-interconnection-agreement-for-107-3-mw-venus-mill-20260127
  2. interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2374
  3. renewablesinfo.org/plant/65788

Commercial operation date: Only LBNL queue data provides a COD target of 2027-12-31. No news sources provide an updated or alternative COD estimate.

Developer: PUCT filing (Jan 2026) shows interconnection agreement between Oncor and 'AIH Texas Acquisitions, LLC' as the legal entity. Multiple sources (Cleanview news, renewablesinfo.org) identify Key Capture Energy as the operating company/owner.

Status: LBNL shows 'active' status. PUCT filing confirms Standard Generation Interconnection Agreement was executed between Oncor and AIH Texas Acquisitions LLC on 1/23/2026, and Cleanview news (Jan 27, 2026) reports IA signing for 107.3 MW capacity.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Venus Mill Storage project is a proposed 100.8 MW battery energy storage system located in Ellis County, Texas. The project, developed by KCE TX 14, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0216. It entered the queue on March 14, 2022, with a proposed commercial operation date of December 31, 2027. The project's interconnection status is currently in the Facility Study phase.

The Venus Mill Storage project is linked to the existing TX 14 Venus Mill Storage operating plant (EIA ID 65788). Recent news coverage indicates development activity related to the project.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Ellis

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

—

Utility

—

Entity

ERCOT

Service Type

—

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.