Venus Mill Storage
100.8 MW storage in Ellis, TX · In queue since March 2022 · Proposed COD December 2027
100.8 MW
Capacity
1
Components
Battery
4y 8m
In Queue
—
IA Status
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Projected COD moved
3 times
Jul 2024 → Dec 2027
Net change
+41 months
first report to latest
Capacity
104 → 101 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Standard Generation Interconnection Agreement executed between Oncor and AIH Texas Acquisitions, LLC
interchange.puc.texas.govKey Capture Energy announced signing of interconnection agreement with Oncor for 107.3 MW Venus Mill Storage
cleanview.coResearch sources and reasoning (3 recorded sources)
high confidence at research time
- cleanview.co/news/battery/key-capture-energy-signs-interconnection-agreement-for-107-3-mw-venus-mill-20260127
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2374
- renewablesinfo.org/plant/65788
Commercial operation date: Only LBNL queue data provides a COD target of 2027-12-31. No news sources provide an updated or alternative COD estimate.
Developer: PUCT filing (Jan 2026) shows interconnection agreement between Oncor and 'AIH Texas Acquisitions, LLC' as the legal entity. Multiple sources (Cleanview news, renewablesinfo.org) identify Key Capture Energy as the operating company/owner.
Status: LBNL shows 'active' status. PUCT filing confirms Standard Generation Interconnection Agreement was executed between Oncor and AIH Texas Acquisitions LLC on 1/23/2026, and Cleanview news (Jan 27, 2026) reports IA signing for 107.3 MW capacity.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Venus Mill Storage project is a proposed 100.8 MW battery energy storage system located in Ellis County, Texas. The project, developed by KCE TX 14, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0216. It entered the queue on March 14, 2022, with a proposed commercial operation date of December 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The Venus Mill Storage project is linked to the existing TX 14 Venus Mill Storage operating plant (EIA ID 65788). Recent news coverage indicates development activity related to the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09