Goodalta Solar
221.36 MW generation in Navarro, TX · In queue since January 2021 · Proposed COD September 2027
221.36 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-20
Projected COD moved
5 times
Feb 2023 → Sep 2027
Net change
+55 months
first report to latest
Capacity
185 → 221 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Kerens ISD approved tax value limitation agreement payments for Goodalta Solar Project
themonitor.netTexas Comptroller certification for Chapter 313 tax abatement for 180 MW solar facility near Kerens
assets.comptroller.texas.govResearch sources and reasoning (7 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/solar-farms/texas/23INR0171/goodalta-solar
- interconnection.fyi/project/ercot-23inr0171
- assets.comptroller.texas.gov/ch313/1694/1694-kerens-goodalta-cert.pdf
- themonitor.net/news/kerens-isd-approves-solar-project-payments
- ercotqueue.com/project/23INR0171
- assets.comptroller.texas.gov/ch313/1694/1694-kerens-goodalta-findings.pdf
- comptroller.texas.gov/economy/docs/active-list.xlsx
Commercial operation date: Only LBNL queue snapshot provides a COD of 2027-09-20. No news sources or press releases found with alternative dates. Texas Comptroller documents from 2022 mention the project is 'planned' but provide no specific COD.
Developer: All sources consistently identify GoodAlta Power Center LLC as the developer. No parent company or operating entity identified in any search results. Appears to be a project-specific LLC with no public parent disclosed.
Status: LBNL shows 'Active' status in Facility Study phase. Texas Comptroller documents confirm tax value limitation agreement was approved in 2022, indicating project remains viable, though no recent construction or financing announcements found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Goodalta Solar project is a proposed 221.36 MW solar generation facility in Navarro County, Texas. Developed by GoodAlta Power Center LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0171, with a queue entry date of January 25, 2021. The proposed commercial operation date is September 20, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is tap 138kV 3127 Trinidad - 212 Winkler. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GoodAlta Power Center LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 3127 Trinidad - 212 Winkler
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- TRSES_UNIT6
- POI Substation
- Trinidad Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.