Ringtail Ridge Storage
100.57 MW storage in Kendall, TX · In queue since January 2021 · Proposed COD May 2028
100.57 MW
Capacity
1
Components
Battery
5y 10m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-23
Projected COD moved
4 times
May 2023 → May 2028
Net change
+60 months
first report to latest
Capacity
59 → 101 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Public meeting held with 250+ residents opposing project; County Commissioner pledged to block tax abatements
boernestar.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- boernestar.com/article/7151,comfort-residents-sound-off-on-battery-storage-site-plan
- boernestar.com/article/9257,county-makes-move-to-help-in-fight-against-battery-storage-systems
- boernestar.com/article/7513,campbell-troxclair-pen-letters-opposing-battery-storage-plans
- cleanview.co/developer/key-capture-energy
Commercial operation date: LBNL queue shows proposed COD of 2028-05-23. No news sources provide alternative COD targets; project faces significant local opposition which may delay or cancel development.
Developer: LBNL filing uses project LLC 'KCE TX 26, LLC'. Boerne Star coverage and Cleanview database confirm parent company is Key Capture Energy (KCE), an experienced developer/operator in business since 2016.
Status: LBNL shows 'Active' in Facility Study phase. However, Jan-Oct 2024 Boerne Star coverage documents organized community opposition, county officials opposing tax incentives, and state legislators writing opposition letters, creating significant development risk.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Ringtail Ridge Storage is a proposed 100.57 MW battery storage project located in Kendall County, Texas. The developer is KCE TX 26, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-23INR0163, with an interconnection queue entry date of January 25, 2021. The proposed commercial operation date is May 23, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The Ringtail Ridge Storage project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Kendall
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
KCE TX 26, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7150 Kendall 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HHOLLW2_WND1
- POI Substation
- Horse Hollow Kendall Tie
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.