Cradle Solar
200.85 MW generation in Brazoria, TX · In queue since February 2021 · Proposed COD September 2027
200.85 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Phase
Signed Mar 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 1m
IA → COD
4y 6m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-17
Projected COD moved
4 times
Aug 2023 → Sep 2027
Net change
+49 months
first report to latest
Capacity
225 → 201 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Research sources and reasoning (7 recorded sources)
high confidence at research time
- businesswire.com/news/home/20240327320960/en/Leeward-Renewable-Energy-Signs-Power-Purchase-Agreement-with-Microsoft-for-Morrow-Lake-Solar-and-Cradle-Solar-Facilities
- lreus.com/projects/cradle-solar/
- cradlesolartx.com/
- cleanview.co/power-projects/planned/solar-farms/texas/65822_CRAS0/cradle-solar
- gem.wiki/Cradle_Solar
- pv-magazine-usa.com/2024/04/03/microsoft-signs-two-large-solar-power-purchase-agreements/
- datacenterdynamics.com/en/news/microsoft-signs-400mw-solar-ppa-in-texas/
Commercial operation date: LBNL proposed COD of 2027-09-17 aligns with multiple sources citing 2027 expected online date (Cleanview, GEM wiki). Microsoft PPA signed March 2024 for project under development supports this timeline.
Developer: LBNL filing entity is 'Cradle Solar LLC' (project SPV), but Leeward Renewable Energy's website lists Cradle Solar as their project, and BusinessWire March 2024 confirms 'Leeward Renewable Energy Signs Power Purchase Agreement with Microsoft for...Cradle Solar Facilities.'
Status: LBNL shows IA executed 2023-03-15. March 2024 Microsoft PPA announcement and BusinessWire release confirm project is under development with construction phase approaching.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cradle Solar is a proposed 200.85 MW solar generation project located in Brazoria County, Texas. The developer is Cradle Solar LLC. This project is in the ERCOT interconnection queue as entry ERCOT-23INR0150, with a queue entry date of February 4, 2021, and a proposed commercial operation date of February 22, 2027.
The project's Interconnection Agreement (IA) has been executed as of March 15, 2023. Cradle Solar is linked to the existing operating Cradle Solar plant (EIA ID 65822). The point of interconnection is the tap 345kV 42500 Dow - 43035 Oasis ckt 18.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cradle Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 42500 Dow - 43035 Oasis ckt 18
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DOW_61_2_63
- POI Substation