PHOTON SOLAR 3 SLF
109.99 MW generation in Wharton, TX · In queue since October 2020 · Proposed COD May 2026
109.99 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Phase
Signed Oct 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1 year
IA → COD
4y 7m
Total Duration
1 year
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-11
Projected COD moved
11 times
Apr 2023 → May 2026
Net change
+37 months
first report to latest
Capacity
600 → 110 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Expected online date per Texas PUC generation table
ftp.puc.texas.govResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
- renewablesinfo.org/project/ercot-23inr0111-photon-solar-3-slf
- ercotqueue.com/project/23INR0111
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
Commercial operation date: LBNL proposed COD is 2026-05-11. Texas PUC gentable.xls (published Jan 2026) lists Feb-26 expected online date. Interconnection.fyi reported a COD change from Dec 2024 to Jun 2025 as of Mar 2025, suggesting ongoing delays. Texas PUC Feb-26 target is most authoritative recent source.
Developer: LBNL filing entity 'GulfStar Power, LLC' matches all research sources. No evidence of shell LLC structure or ownership changes. Ercotqueue.com confirms GulfStar Power, LLC as developer with multiple projects in Wharton County.
Status: LBNL status 'active' with IA executed is confirmed. Renewablesinfo.org lists status as 'Construction Current' and ercotqueue.com shows 'Commissioned' stage with 100% build chance, indicating advanced development.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The PHOTON SOLAR 3 SLF project is a proposed 109.99 MW solar generation project located in Wharton County, Texas. The project is being developed by GulfStar Power, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0111, with a queue entry date of October 23, 2020.
The project's proposed commercial operation date is February 16, 2026. An Interconnection Agreement (IA) has been executed for the project, with an IA date of October 1, 2021. The point of interconnection is the 44880 Waterh_POI_5 345kV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GulfStar Power, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44880 Waterh_POI_5 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.