Iguala Solar (ERCOT-23INR0090) — Project Summary

Queue ID
ERCOT-23INR0090
Capacity
250 MW
Technology
Solar
Status
active
Location
Victoria, TX
Region
ERCOT
Developer
—
IA Status
—

Iguala Solar

ERCOT-23INR0090BetaActiveSolarERCOTLBNL + Live

250 MW generation in Victoria, TX · In queue since October 2020 · Proposed COD February 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

250 MW

Capacity

1

Components

Solar

6y 1m

In Queue

—

IA Status

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 4m

Pre-Study0%
Queue EntryOct 6, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-02-01

Queue history
23INR0090 · 62 monthly ERCOT reports, Jun 2021 – Sep 2026

Projected COD moved

3 times

Jun 2023 → Feb 2029

Net change

+68 months

first report to latest

Capacity

250 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 7, 2020
Interconnection agreement signedJul 29, 2025
On ERCOT's inactive listDec 2025 – Jan 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2027
Differs from queue: Feb 1, 2029
Developer in saved assessment
—
From queue filing
Status at research time
Active
Active — Interconnection Agreement executed with AEP Texas in August 2025, tax abatement approved, targeting 2027 COD
Financing
Not recorded

Milestones in this assessment

Permit approvedSep 2022

Texas Comptroller certified completed Chapter 313 tax abatement application for 250 MW solar + battery project

assets.comptroller.texas.gov
IA executedAug 2025

ERCOT Standard Generation Interconnection Agreement executed between AEP Texas and Iguala Solar LLC

interchange.puc.texas.gov
COD target2027Latest in this assessment

ERCOT capacity planning chart lists 250 MW solar project with 2027 expected online date

ercot.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. assets.comptroller.texas.gov/ch313/1802/1802-bloomington-iguala-app.pdf
  2. assets.comptroller.texas.gov/ch313/1802/1802-bloomington-iguala-cert.pdf
  3. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&ItemMatch=Equal&DocumentType=ALL&SortBy=FilingParty&SortOrder=Ascending
  4. ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025.xlsx
  5. files-backend.assets.thrillshare.com/documents/asset/uploaded_file/2437/Bisd/29cd544e-ae00-4494-be3c-dd7a07e9555c/Board_Minutes_for_Public_Mtg_November_14__202.DOCX?disposition=inline

Commercial operation date: ERCOT capacity chart from December 2025 lists Iguala Solar with 2027 COD, which is 2 years earlier than LBNL's 2029-02-01 proposed date. This represents a more current target from ERCOT's own planning documents.

Developer: All sources reference only 'Iguala Solar LLC' as the project entity. No parent company or operating developer is identified in tax filings, PUC documents, or ERCOT records. Cleanview lists it under Recurrent Energy's pipeline, but this is unconfirmed by primary sources.

Status: PUC filings show ERCOT Standard Generation Interconnection Agreement between AEP Texas and Iguala Solar LLC filed in August 2025, indicating active progression through interconnection process. Texas Comptroller records show completed Chapter 313 tax abatement application process in 2022.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Iguala Solar project is a proposed 250 MW solar generation facility located in Victoria County, Texas. The project, developed by Iguala Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0090, with a queue entry date of October 7, 2020. The proposed commercial operation date is September 1, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 345kV 5915 STP - 8249 Angstrom. The Iguala Solar project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Victoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

—

Utility

—

Entity

ERCOT

Service Type

—

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.