Nockenut Springs Solar 1
203.17 MW generation in Guadalupe, TX · In queue since September 2020 · Proposed COD June 2029
203.17 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Phase
Signed Nov 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 2m
IA → COD
5y 7m
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2029-06-05
Projected COD moved
3 times
Dec 2023 → Jun 2029
Net change
+66 months
first report to latest
Capacity
203 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Target commercial operation date per ERCOT MORA report
ercot.comResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-23inr0088
- cleanview.co/power-projects/planned/solar-farms/texas/23INR0088/nockenut-springs-solar-1
- ercotqueue.com/project/23INR0088
- ercot.com/files/docs/2026/05/01/MORA_July2026.pdf
- ercot.com/files/docs/2026/01/08/Capacity-Changes-by-Fuel-Type-Charts_December_2025.xlsx
- ercot.com/files/docs/2025/04/04/Capacity-Changes-by-Fuel-Type-Charts_March_2025.xlsx
Commercial operation date: LBNL queue snapshot shows proposed COD of 2029-06-05. ERCOT MORA document from May 2026 confirms 2029 target. No contradictory signals found in research; all sources echo the LBNL date.
Developer: All sources consistently identify developer as Pecan Springs Energy, LLC. No evidence of shell-LLC structure or parent company differentiation. No ownership changes detected.
Status: LBNL shows 'active' status with IA executed 2023-11-17. Ercotqueue.com confirms 'IA + FIS complete'. No press releases or construction announcements found, suggesting pre-construction phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Nockenut Springs Solar 1 is a proposed solar generation project with a total capacity of 203.17 MW. The project, located in Guadalupe County, Texas, is being developed by Pecan Springs Energy, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0088, with a queue entry date of September 25, 2020. The proposed commercial operation date is June 5, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Nockenut Springs Solar 1 is the tap 345kV 5133 Elm Creek - 5915 STP ckt 1. The project has appeared in recent news coverage regarding energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Guadalupe
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pecan Springs Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 5133 Elm Creek - 5915 STP ckt 1
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Elm Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Nockenut Springs Solar 1
Data-driven briefing on Nockenut Springs Solar 1 — fleet, generation, financial, and news signals.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.