Bottom Grass Solar
508.61 MW hybrid in Colorado, TX · In queue since November 2020 · Proposed COD March 2028
508.61 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Phase
Signed Jun 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 7m
IA → COD
4y 9m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-03-01
Projected COD moved
7 times
Jul 2023 → Mar 2028
Net change
+56 months
first report to latest
Capacity
258 → 509 MW
changed in the reports
Latest stage
Cancelled
last listed Jan 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
medium confidence at research time
- hmgroup.com/news/hm-group-signs-virtual-power-purchase-agreement-with-lightsource-bp-enabling-the-construction-of-new-renewable-energy-infrastructure-in-texas/
- interconnection.fyi/project/ercot-23inr0082
Commercial operation date: No post-LBNL source gives a COD. The H&M/Lightsource bp VPPA coverage (Oct 2024) says the deal enables construction but gives no date in the available extract. The LBNL proposed COD of 2028-03-01 is retained as the only date.
Developer: The H&M Group press item (2024-10-31) names Lightsource bp as the seller and developer on the virtual PPA for this project. The LBNL filing entity, Bottom Grass Solar Project, LLC, is a project shell. No acquisition or transfer is documented.
Status: LBNL shows active with an executed IA, and the only primary corporate source points to construction-stage progress. The aggregator 'withdrawn' flag is uncorroborated and likely reflects a different snapshot or the sibling BESS queue entry (23INR0083). Ground-level construction progress is not confirmed by an independent source.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Bottom Grass Solar is a proposed solar generation project located in Colorado County, Texas, with a total capacity of 508.61 MW. Developed by Bottom Grass Solar Project, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0082, with a queue entry date of November 5, 2020. The proposed commercial operation date is December 1, 2026. The interconnection agreement for the project was executed on June 29, 2023.
The Bottom Grass Solar project has been the subject of recent news coverage, with eight articles published in industry and deals categories.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jan 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Colorado
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bottom Grass Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 9073 Holman - 44200 Hillje
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Holman Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.