Shaw Solar
124.65 MW generation in Bandera, TX · In queue since October 2020 · Proposed COD October 2026
124.65 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Phase
Signed Feb 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 4m
IA → COD
3y 8m
Total Duration
2y 4m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2026-10-16
Projected COD moved
5 times
Oct 2023 → Oct 2026
Net change
+36 months
first report to latest
Capacity
120 → 125 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT
interconnection.fyiResearch sources and reasoning (2 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-23inr0078
- cleanview.co/power-projects/planned/solar-farms/texas/23INR0078/shaw-solar
Commercial operation date: LBNL queue snapshot shows proposed COD of 2026-04-29 with IA executed in Feb 2023. No news coverage or press releases found for this specific utility-scale project; search results returned unrelated residential solar installers and community solar projects with the same name.
Developer: Only source is LBNL filing showing Rio Lago Solar, LLC as developer. No news coverage, corporate announcements, or ownership information found. Unable to determine if this is a shell LLC or operating entity due to complete absence of public information.
Status: LBNL shows active status with executed interconnection agreement as of Feb 2023. However, complete absence of press releases, permitting news, or construction updates suggests project may be in early development or quietly progressing without public disclosure.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Shaw Solar is a proposed solar generation project located in Bandera County, Texas, with a total capacity of 124.65 MW. The project, developed by Rio Lago Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0078, with a queue entry date of October 23, 2020. The proposed commercial operation date is April 29, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The Shaw Solar project has been the subject of recent news coverage, with five articles related to the industry, deals, and development of the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bandera
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rio Lago Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 7146 Verde Creek - 7438 Bandera
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Verde Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.