Charger Solar (ERCOT-23INR0047) — Project Summary

Queue ID
ERCOT-23INR0047
Capacity
397.15 MW
Technology
Solar
Status
active
Location
Refugio, TX
Region
ERCOT
Developer
AP Solar 4, LLC
IA Status
IA Executed

Charger Solar

ERCOT-23INR0047BetaActiveSolarERCOTLBNL + Live

397.15 MW generation in Refugio, TX · In queue since June 2020 · Proposed COD September 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

397.15 MW

Capacity

1

Components

Solar

6y 5m

In Queue

IA Executed

IA Phase

Signed Jun 2021

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1 year

IA → COD

5y 3m

Total Duration

1 year

Schedule

2 months past proposed COD

Construction75%
Queue EntryJun 19, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 5, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-09-18

Queue history
23INR0047 · 72 monthly ERCOT reports, Jun 2020 – Sep 2026

Projected COD moved

6 times

Mar 2023 → Sep 2026

Net change

+42 months

first report to latest

Capacity

408 → 397 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 19, 2020
Facilities study approvedSep 22, 2025
Interconnection agreement signedJun 5, 2021
Approved for energizationJun 30, 2026
Approved for synchronizationJul 17, 2026
On ERCOT's inactive listMay 2024 – Aug 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Sep 18, 2026
From queue filing
Developer in saved assessment
J-POWER USA (J-POWER North America Holdings Co., Ltd., subsidiary of Electric Power Development Co. / J-POWER)
Ownership change in saved research
Status at research time
Active
Active, IA executed 2021-06-05. J-POWER announced a decision to construct in Sept 2025, but no groundbreaking is confirmed and Global Energy Monitor lists the project as cancelled (likely stale).
Financing
Not recorded
Ownership history
  1. 2025-09·AP Solar Holdings / J-POWER USA / SPDI / Avondale (joint venture)→J-POWER North America Holdings Co., Ltd. (JPUSA), sole developerjpower.co.jp
Research sources and reasoning (6 recorded sources)

low confidence at research time

  1. jpower.co.jp/english/news_release/pdf/news250902e.pdf
  2. jpowerusa.com/projects/charger-solar/
  3. gem.wiki/Charger_Solar
  4. cleanview.co/power-projects/planned/solar-farms/texas/23INR0047/charger-solar
  5. solarpowerworldonline.com/2020/08/j-power-usa-400-megawatt-texas-solar-project/
  6. saurenergy.com/solar-energy-news/j-power-spdi-avondale-ap-solar-to-develop-400-mw-solar-project-in-texas

Commercial operation date: Only the LBNL proposed COD (2026-09-18) gives a date. Cleanview's 'Expected online 2026' appears to be derived from the same data, and J-POWER's Sept 2, 2025 press release (excerpt) states a decision to construct but no COD. A Sept 2025 construction decision makes a Sept 2026 COD look optimistic, but no source gives a revised date.

Developer: In 2020 the project was a JV of J-POWER USA, SPDI, Avondale and AP Solar Holdings, and AP Solar 4, LLC is the AP Solar project shell. J-POWER's Sept 2025 release says it is building the project through its 100% owned subsidiary JPUSA and calls it 'the first renewable one developed solely by J-POWER', which implies the partners were bought out. The JPUSA project page still says 'jointly develop' with AP Solar Holdings and is undated, so the exact buyout date is unconfirmed.

Status: LBNL shows Active with an executed IA, and J-POWER's Sept 2025 release is the most recent primary-source signal of a go-ahead. Global Energy Monitor's 'cancelled' label conflicts with it, but there is no corroborating cancellation or withdrawal evidence. Construction start is also unconfirmed, so Active is kept rather than Construction.

Project lifecycle
as of 2026-04-02
TechnologySolarInside Climate News · 2026-04-02

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Charger Solar is a proposed 397.15 MW solar generation project located in Refugio County, Texas. The developer is AP Solar 4, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-23INR0047, with a queue entry date of June 19, 2020. The proposed commercial operation date is August 31, 2026.

The project's interconnection agreement has been executed as of June 5, 2021. Charger Solar has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Refugio

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

AP Solar 4, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 8249 Angstrom – 5915 STP

Data Source

LBNL + Live

DeveloperAP Solar HoldingsSolar Power World · 2020-08-05
CompanyEvergypv magazine USA · 2020-08-06
AgencyAlabama Public Service CommissionInside Climate News · 2026-04-02
RulingOrderInside Climate News · 2026-04-02
TransactionJoint ventureSolar Power World · 2020-08-05
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (3)Beta

Last updated 2026-04-09