TE Smith Storage
125.36 MW storage in Rockwall, TX · In queue since September 2021 · Proposed COD January 2026
125.36 MW
Capacity
1
Components
Battery
4y 10m
In Queue
IA Executed
IA Phase
Signed Nov 2023
Queue → IA
2y 2m
IA → COD
2y 2m
Total Duration
2y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-01-15
The TE Smith Storage project is a proposed 125.36 MW battery storage project located in Rockwall County, Texas. The developer is BT Smith Storage, LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0555, with an interconnection queue entry date of September 2, 2021, and a proposed commercial operation date of January 15, 2026. The project's Interconnection Agreement (IA) was executed on November 8, 2023.
The TE Smith Storage project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Rockwall
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Smith Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
2483 Royse Switch 345kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about TE Smith StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.