TE Smith Storage
125.36 MW storage in Rockwall, TX · In queue since September 2021 · Proposed COD January 2026
125.36 MW
Capacity
1
Components
Battery
5y 2m
In Queue
IA Executed
IA Phase
Signed Nov 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 2m
IA → COD
2y 2m
Total Duration
2y 2m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-01-15
Projected COD moved
8 times
Dec 2022 → Jan 2026
Net change
+37 months
first report to latest
Capacity
405 → 125 MW
changed in the reports
Latest stage
Commercial operation
last listed Feb 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Project listed as operational in ERCOT October 2025 capacity chart
ercot.comResearch sources and reasoning (4 recorded sources)
high confidence at research time
- ercot.com/files/docs/2025/11/06/Capacity-Changes-by-Fuel-Type-Charts_October_2025_PlannedMonthly.xlsx
- cleanview.co/power-projects/operating/battery-storage-projects/texas/69329/te-smith-storage
- interconnection.fyi/project/ercot-22inr0555
- eia.gov/electricity/monthly/epm_table_grapher.php?t=table_6_03
Commercial operation date: LBNL proposed COD is 2026-01-15, but ERCOT's October 2025 capacity chart lists TE Smith Storage as operational in 2025, and Cleanview reports it 'became operational in 2026'. EIA data (Result 8) shows it as operational. The project appears to have come online in late 2025/early 2026, roughly on schedule.
Developer: All sources consistently identify 'BT Smith Storage LLC' as both the filing entity and operator. No parent company or shell-LLC distinction found in any research. This appears to be a single-purpose project entity with no disclosed parent.
Status: LBNL shows 'active' with IA executed 2023-11-08, but multiple independent sources (ERCOT capacity chart Result 5, EIA database Result 8, Cleanview Result 7, interconnection.fyi Result 3) confirm the project is now operational.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The TE Smith Storage project is a proposed 125.36 MW battery storage project located in Rockwall County, Texas. The developer is BT Smith Storage, LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0555, with an interconnection queue entry date of September 2, 2021, and a proposed commercial operation date of January 15, 2026. The project's Interconnection Agreement (IA) was executed on November 8, 2023.
The TE Smith Storage project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Feb 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Rockwall
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Smith Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
2483 Royse Switch 345kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- V2_DGR1_RN
- POI Substation
- Royse Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.