Lane City Wind
199.5 MW generation in Wharton, TX · In queue since April 2021 · Proposed COD December 2026
199.5 MW
Capacity
1
Components
Wind
5y 7m
In Queue
IA Executed
IA Phase
Signed May 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 1m
IA → COD
4y 7m
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-31
Projected COD moved
4 times
Dec 2022 → Dec 2026
Net change
+48 months
first report to latest
Capacity
207 → 200 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Project commissioned as part of RWE's 2 GW portfolio brought online in 2025
pv-magazine-usa.comResearch sources and reasoning (7 recorded sources)
high confidence at research time
- pv-magazine-usa.com/2026/03/06/rwe-americas-touts-2-gw-of-clean-energy-projects-commissioned-in-2025/
- baycitytribune.com/news/rwe-brings-wind-power-to-matagorda-county-as-grid-demand-climbs/article_aca6953d-9872-4795-9ad0-68285ad8d0c9.html
- solarquarter.com/2026/04/02/rwe-expands-its-u-s-clean-energy-portfolio-by-2-gw-in-2025-lifting-national-capacity-to-over-12-7-gw/
- gem.wiki/Lane_City_Wind
- assets.comptroller.texas.gov/ch313/1848/1848-wharton-lane-appsupp1.pdf
- facebook.com/whartonpost/posts/wind-projects-completed-in-wharton-matagorda-countiesenergy-company-rwe-announce/906869892112738/
- interchange.puc.texas.gov/Documents/57696_1_1467980.PDF
Commercial operation date: Multiple sources confirm the project came online in 2025: RWE's March 2026 press release states it commissioned 2 GW including this project in 2025, Global Energy Monitor lists it as 'operating', and local news confirms completion. LBNL's 2025-12-30 target aligns with actual 2025 commissioning.
Developer: LBNL filing entity is 'Lane City Wind, LLC' (project SPV per Texas tax documents), while all press releases and operational announcements identify the parent operator as 'RWE Clean Energy' / 'RWE Americas'. Standard project-finance structure.
Status: LBNL shows 'active' with IA executed, but multiple 2026 sources confirm the project is now operational: RWE's March 2026 press release announcing 2 GW commissioned in 2025, Global Energy Monitor listing as 'operating', and local news coverage of completion.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Lane City Wind project is a proposed 199.5 MW wind generation project located in Wharton County, Texas. Developed by RWE Clean Energy, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-22INR0517. The project entered the interconnection queue on April 26, 2021, and has a proposed commercial operation date of December 30, 2025.
The project's Interconnection Agreement (IA) was executed on May 13, 2022. The point of interconnection is the 44040 Bailey 345kV substation. This proposed project is linked to the existing Lane City Wind operating plant (EIA ID 67443). The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Clean Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44040 Bailey 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- South Lane City Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Max 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
FPL Energy Oliver Wind I LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.