Gransolar Texas One
50.8 MW generation in Milam, TX · In queue since March 2021 · Proposed COD April 2025
50.8 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Jun 2022
Queue → IA
1y 3m
IA → COD
2y 10m
Total Duration
1y 3m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-04-25
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Gransolar Texas One project is a proposed 50.8 MW solar generation project located in Milam County, Texas. The developer is Gransolar Texas One, LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-22INR0511, with a queue entry date of March 16, 2021, and a proposed commercial operation date of April 25, 2025. The project's Interconnection Agreement (IA) has been executed as of June 13, 2022.
The project is linked to the existing Gransolar Texas One, LLC operating plant (EIA ID 68244). The point of interconnection is Tap 138kV 3659 Thorndale North - 116 Salty. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas One, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3659 Thorndale North - 116 Salty
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GRAN_SLR_RN
- POI Substation
- Salty Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Gransolar Texas OneForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.