Barton Branch IA (ERCOT-22INR0504) — Project Summary

Queue ID
ERCOT-22INR0504
Capacity
203.62 MW
Technology
Battery
Status
active
Location
Robertson, TX
Region
ERCOT
Developer
Barton Branch IA LLC
IA Status
IA Executed

Barton Branch IA

ERCOT-22INR0504BetaActiveBatteryERCOTLBNL + Live

203.62 MW storage in Robertson, TX · In queue since March 2021 · Proposed COD October 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

203.62 MW

Capacity

1

Components

Battery

5y 8m

In Queue

IA Executed

IA Phase

Signed Jun 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4y 3m

IA → COD

1y 4m

Total Duration

4y 3m

Schedule

2 months past proposed COD

Construction75%
Queue EntryMar 16, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 18, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-10-01

Queue history
22INR0504 · 67 monthly ERCOT reports, Mar 2021 – Sep 2026

Projected COD moved

8 times

Feb 2022 → Oct 2026

Net change

+56 months

first report to latest

Capacity

102 → 204 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 16, 2021
Facilities study approvedJun 16, 2025
Interconnection agreement signedJun 18, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Nov 2026
Differs from queue: Oct 1, 2026
Developer in saved assessment
Jupiter Power
Filed as Barton Branch IA LLC
Status at research time
IA Executed
IA Executed — construction started March 2026, targeting November 2026 COD
Financing
Secured
Financing secured to support construction start in March 2026; specific terms not publicly disclosed

Milestones in this assessment

IA executedJun 18, 2025

ERCOT Standard Generation Interconnection Agreement executed between Barton Branch IA LLC and Texas-New Mexico Power Company

interchange.puc.texas.gov
Permit approvedJul 22, 2025

Robertson County approved tax abatement at 50% discount with PILOT payment of $168,943

facebook.com
GroundbreakingMar 2026

Jupiter Power began construction on 200 MW battery energy storage project in Robertson County

cleanview.co
COD targetNov 2026Latest in this assessment

ERCOT planning documents show expected online date of 2026

ercot.com
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. cleanview.co/news/battery/jupiter-power-begins-construction-on-200-mw-barton-branch-ia-in-tx-20260303
  2. co.robertson.tx.us/upload/page/5864/2025/public_hearing__barton_branch_ia_llc__tax_abatement_agreement__72225.pdf
  3. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
  4. facebook.com/61580767825138/posts/action-itemsee-link-in-this-post-below-for-submitting-comments-for-this-hearing/122109319743025594/
  5. ercot.com/files/docs/2025/11/06/Capacity-Changes-by-Fuel-Type-Charts_October_2025_PlannedMonthly.xlsx

Commercial operation date: LBNL proposed COD is 2026-10-01. Construction began March 2026 per Jupiter Power announcement, and ERCOT planning documents show November 2026 expected online date. Consensus is November 2026, one month later than LBNL filing.

Developer: LBNL filing entity is 'Barton Branch IA LLC' (project SPV). March 2026 construction announcement clearly identifies Jupiter Power as the operating developer breaking ground on the project.

Status: LBNL status 'IA Executed' (June 2025) is accurate. Jupiter Power construction announcement from March 2026 confirms project has moved from development to active construction phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Tidwell Prairie III Batt project is a proposed 200 MW battery storage project located in Robertson County, Texas. Developed by Tidwell Prairie III LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-22INR0504. The project entered the interconnection queue on March 16, 2021, and has a proposed commercial operation date of October 1, 2026. Its interconnection status is currently in the Facility Study phase.

The development project consists of a 200 MW battery energy storage system. The point of interconnection is at the Tap 345kV 3400 Twin Oak - 39950 TNP One. The project is currently listed as active within the ERCOT interconnection queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Robertson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Barton Branch IA LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 3400 Twin Oak - 39950 TNP One

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
HIGH
Nearest Node (Estimated)
TDWLPR_1_RN
POI Substation
Phillips Coal Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.