TEXPO
680 MW generation in Wilbarger, TX · In queue since March 2021 · Proposed COD October 2027
680 MW
Capacity
1
Components
Gas
5y 8m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
Projected COD moved
5 times
Feb 2023 → Oct 2027
Net change
+56 months
first report to latest
Capacity
680 MW
unchanged in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- ercotqueue.com/project/22INR0497
- interchange.puc.texas.gov/Documents/59029_216_1579005.PDF
- interconnection.fyi/project/ercot-22inr0497
Commercial operation date: Only the LBNL snapshot gives a COD (2027-10-31). The search results are mostly noise about unrelated Texpo Energy (a retail electricity provider) and TEXPO conferences. Trackers like ercotqueue.com and the PUC document show no IA and a Facility Study underway, which makes the date look optimistic, but no source offers a replacement.
Developer: ercotqueue.com and the PUC Interchange document both list Oklaunion Power Station, LLC as the developer, which matches LBNL. No press release names a parent or operating company, so no shell-vs-parent correction can be made.
Status: LBNL lists the project as active, and the PUC Interchange and ercotqueue.com entries say the same (SS completed, FIS started, no IA). No withdrawal or construction signals were found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The TEXPO project is a proposed 680 MW natural gas generation project in Wilbarger County, Texas. Developed by Oklaunion Power Station, LLC, the project entered the ERCOT interconnection queue as ERCOT-22INR0497 on March 16, 2021. Its proposed commercial operation date is October 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project is to be located at the Point of Interconnection (POI) 6100 Oklaunion 345kV. The TEXPO project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Oklaunion Power Station, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6100 Oklaunion 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DC_N
- POI Substation
- Oklaunion North Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.