TEXPO
680 MW generation in Wilbarger, TX · In queue since March 2021 · Proposed COD October 2027
680 MW
Capacity
1
Components
Gas
5y 4m
In Queue
Facility Study
IA Phase
COD target: 2027
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
The TEXPO project is a proposed 680 MW natural gas generation project in Wilbarger County, Texas. Developed by Oklaunion Power Station, LLC, the project entered the ERCOT interconnection queue as ERCOT-22INR0497 on March 16, 2021. Its proposed commercial operation date is October 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project is to be located at the Point of Interconnection (POI) 6100 Oklaunion 345kV. The TEXPO project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Oklaunion Power Station, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6100 Oklaunion 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DC_N
- POI Substation
- Oklaunion North Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.