TEXPO (ERCOT-22INR0497) — Project Summary

Queue ID
ERCOT-22INR0497
Capacity
680 MW
Technology
Gas
Status
active
Location
Wilbarger, TX
Region
ERCOT
Developer
Oklaunion Power Station, LLC
IA Status
Facility Study

TEXPO

ERCOT-22INR0497BetaActiveGasERCOTLBNL + Live

680 MW generation in Wilbarger, TX · In queue since March 2021 · Proposed COD October 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

680 MW

Capacity

1

Components

Gas

5y 8m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 7m

Facilities Study50%
Queue EntryMar 16, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-31

Queue history
22INR0497 · 59 monthly ERCOT reports, Nov 2021 – Sep 2026

Projected COD moved

5 times

Feb 2023 → Oct 2027

Net change

+56 months

first report to latest

Capacity

680 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 16, 2021
Facilities study approvedSep 17, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Oct 31, 2027
From queue filing
Developer in saved assessment
Oklaunion Power Station, LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue; screening study complete, Facility Impact Study started, no Interconnection Agreement executed yet (per PUC Interchange Jan 2026 listing).
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. ercotqueue.com/project/22INR0497
  2. interchange.puc.texas.gov/Documents/59029_216_1579005.PDF
  3. interconnection.fyi/project/ercot-22inr0497

Commercial operation date: Only the LBNL snapshot gives a COD (2027-10-31). The search results are mostly noise about unrelated Texpo Energy (a retail electricity provider) and TEXPO conferences. Trackers like ercotqueue.com and the PUC document show no IA and a Facility Study underway, which makes the date look optimistic, but no source offers a replacement.

Developer: ercotqueue.com and the PUC Interchange document both list Oklaunion Power Station, LLC as the developer, which matches LBNL. No press release names a parent or operating company, so no shell-vs-parent correction can be made.

Status: LBNL lists the project as active, and the PUC Interchange and ercotqueue.com entries say the same (SS completed, FIS started, no IA). No withdrawal or construction signals were found.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The TEXPO project is a proposed 680 MW natural gas generation project in Wilbarger County, Texas. Developed by Oklaunion Power Station, LLC, the project entered the ERCOT interconnection queue as ERCOT-22INR0497 on March 16, 2021. Its proposed commercial operation date is October 31, 2027. The project's interconnection status is currently in the Facility Study phase.

The proposed project is to be located at the Point of Interconnection (POI) 6100 Oklaunion 345kV. The TEXPO project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wilbarger

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Oklaunion Power Station, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

6100 Oklaunion 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
DC_N
POI Substation
Oklaunion North Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.