Anson BAT
153.55 MW generation in Jones, TX · In queue since December 2020 · Proposed COD December 2027
153.55 MW
Capacity
1
Components
Battery
5y 11m
In Queue
IA Executed
IA Phase
Signed Aug 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 8m
IA → COD
3y 4m
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-01
Projected COD moved
6 times
Dec 2023 → Dec 2027
Net change
+48 months
first report to latest
Capacity
152 → 154 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
200MW PPA with Meta announced for Anson 2 solar project in Jones County
prnewswire.comERCOT planning document lists Anson BAT COD as May 29, 2026
ercot.comResearch sources and reasoning (4 recorded sources)
high confidence at research time
- prnewswire.com/news-releases/engie-and-meta-announce-new-200-mw-renewable-energy-agreement-expanding-existing-relationship-to-meet-growing-power-demand-302348660.html
- pv-tech.org/engie-meta-ink-200mw-solar-pv-eapa-in-texas/
- ercot.com/files/docs/2025/03/14/EIR-BTU-Texas-A-M-University-System-RELLIS-Campus-Reliability-Project-Scope-RPG-Mar-2025.pdf
- esgtoday.com/meta-buys-100-of-renewable-energy-from-new-900-million-texas-solar-project/
Commercial operation date: LBNL shows 2027-12-01, but ERCOT planning document (Mar 2025) lists Anson BAT with COD 05/29/2026, indicating a ~1.5 year acceleration. The IA was executed in Aug 2024, making the earlier 2026 date more credible.
Developer: LBNL filing uses project LLC 'Anson II Storage LLC'. PR Newswire (Jan 2025) and PV Tech confirm ENGIE owns and operates 'Anson 2 solar project' in Jones County, TX, with a 200MW Meta PPA. The naming match (Anson 2/Anson II) and location confirm ENGIE is the parent developer.
Status: LBNL status 'IA Executed' (Aug 2024) is accurate. ENGIE-Meta PPA announcement (Jan 2025) confirms active development with offtake secured, supporting progression toward construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Anson BAT project is a proposed 150.6 MW battery storage project located in Jones County, Texas. The developer is Anson II Storage LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0457, with an interconnection queue entry date of December 3, 2020. The proposed commercial operation date is December 1, 2027.
The project's Interconnection Agreement (IA) has been executed as of August 15, 2024. The point of interconnection is at the tap 345 kV 68004 Phantom Hill station. The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anson II Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68004 Phantom Hill station
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Anson BATForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.