Anson BAT
153.55 MW generation in Jones, TX · In queue since December 2020 · Proposed COD December 2027
153.55 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Phase
Signed Aug 2024
Queue → IA
3y 8m
IA → COD
3y 4m
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-01
The Anson BAT project is a proposed 150.6 MW battery storage project located in Jones County, Texas. The developer is Anson II Storage LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0457, with an interconnection queue entry date of December 3, 2020. The proposed commercial operation date is December 1, 2027.
The project's Interconnection Agreement (IA) has been executed as of August 15, 2024. The point of interconnection is at the tap 345 kV 68004 Phantom Hill station. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anson II Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68004 Phantom Hill station
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Anson BATForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.