Delaware Ranch Solar
36 MW generation in Culberson, TX · In queue since December 2020 · Proposed COD December 2026
36 MW
Capacity
1
Components
Solar
5y 5m
In Queue
IA Executed
IA Phase
Signed Feb 2022
Queue → IA
1y 2m
IA → COD
4y 10m
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-16
The DR Solar project is a proposed 36 MW solar generation project located in Culberson County, Texas. The developer is Delaware Ranch Solar, LLC. This project is actively listed in the ERCOT interconnection queue as entry ERCOT-22INR0454, with a queue entry date of December 22, 2020.
The proposed commercial operation date is December 16, 2026. The project has an executed Interconnection Agreement (IA), which was executed on February 7, 2022. The point of interconnection is the Delaware River SW (11112) substation.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Culberson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Delaware Ranch Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Delaware River SW (11112)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.