SPC Bloom BESS
100 MW storage in Victoria, TX · In queue since December 2020 · Proposed COD April 2027
100 MW
Capacity
1
Components
Battery
5y 11m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-07
Projected COD moved
3 times
Apr 2022 → Apr 2027
Net change
+60 months
first report to latest
Capacity
100 MW
unchanged in the reports
Latest stage
Cancelled
last listed Feb 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Original proposed completion date before slip to April 2027
interconnectionfyi.substack.comRevised proposed completion date (updated from Nov 2024)
interconnectionfyi.substack.comResearch sources and reasoning (4 recorded sources)
high confidence at research time
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
- interconnection.fyi/projects/state/TX/victoria-county
- renewablesinfo.org/project/ercot-22inr0445-spc-bloom-bess
- ercot.com/files/docs/2025/07/28/EIR-STEC-Ammonia-Plant-Load-Project_SCOPE_July2025_RPG.pdf
Commercial operation date: LBNL queue shows April 2027 COD. Interconnection.fyi noted a slip from Nov 2024 to April 2027, but no independent developer announcement confirms current target. Multiple sources now list project as 'Withdrawn'.
Developer: Only LBNL filing entity 'BRP Blue Topaz 2, LLC' appears across all sources. No parent company or operating entity identified in search results. BRP appears to be the actual developer, not a shell LLC.
Status: LBNL shows 'active' but interconnection.fyi and renewablesinfo.org both explicitly list status as 'Withdrawn'. The discrepancy suggests LBNL snapshot predates withdrawal.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SPC Bloom BESS project is a proposed 100 MW battery storage project located in Victoria County, Texas. The developer is BRP Blue Topaz 2, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0445, with a queue entry date of December 3, 2020. The proposed commercial operation date is April 7, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 100 MW of battery storage capacity. It is interconnected to the grid at the 8911 Black Bayou 138kV point of interconnection. The SPC Bloom BESS project has appeared in recent news coverage regarding energy storage developments in the ERCOT region.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Feb 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Blue Topaz 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8911 Black Bayou 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Black Bayou Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SPC Bloom BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.