TORMES SOLAR
356.6 MW generation in Navarro, TX · In queue since October 2020 · Proposed COD March 2027
356.6 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Phase
Signed Apr 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 6m
IA → COD
2y 11m
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-31
Projected COD moved
3 times
Dec 2023 → Mar 2027
Net change
+39 months
first report to latest
Capacity
381 → 357 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
- —·Lightsource bp→Matrix Renewablesmatrixrenewables.com
Milestones in this assessment
Interconnection agreement executed for the 356.6 MW Tormes Solar queue entry (ERCOT 22INR0437).
interconnection.fyiMatrix Renewables and SOLV Energy began construction on the 457 MWdc Tormes Solar project in Navarro County, TX.
matrixrenewables.comResearch sources and reasoning (8 recorded sources)
medium confidence at research time
- matrixrenewables.com/matrix-renewables-and-solv-energy-break-ground-on-457-mwdc-tormes-solar-project-in-navarro-county-texas/
- pv-tech.org/matrix-renewables-solv-energy-break-ground-on-457mw-texas-solar-project/
- solarpowerworldonline.com/2026/05/matrix-renewables-and-solv-start-construction-on-457-mw-texas-solar-project/
- constructionreviewonline.com/750m-457-mw-tormes-solar-project-breaks-ground-in-texas/
- ess-news.com/2026/06/29/matrix-renewables-secures-1-3-billion-for-us-solar-storage-portfolio/
- solarbuildermag.com/news/mccarthy-named-epc-for-two-utility-scale-solar-farms-in-texas-by-lightsource-bp/
- interconnection.fyi/project/ercot-22inr0437
- cleanview.co/power-projects/planned/solar-farms/texas/22INR0437/tormes-solar
Commercial operation date: The search results give no explicit post-LBNL COD. Construction started in May 2026, and Cleanview and interconnection.fyi still show a 2027 / 2027-03-31 online date, which is consistent with the LBNL date. That date is the ERCOT queue value and is not an independent developer target.
Developer: A 2021 Solar Builder article names Lightsource bp as developer, with McCarthy as EPC. The May 2026 groundbreaking announcements name Matrix Renewables as developer, with SOLV Energy as EPC, so the project appears to have changed hands. The transaction date is not in the sources, and the LBNL filing entity is a project LLC.
Status: Multiple outlets and the Matrix press release (May 28, 2026) report that construction has started on Tormes Solar in Navarro County. The LBNL 'active' status is a queue-position state and understates this.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The TORMES SOLAR project is a proposed 382.12 MW solar generation facility in Navarro County, Texas. The project, developed by BDPU Solar Tormes LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0437, with a queue entry date of October 23, 2020. The proposed commercial operation date is March 31, 2027.
The project's Interconnection Agreement (IA) has been executed as of April 10, 2024. The point of interconnection is at the tap 345kV 1906 Venus - 68091 Navarro. The TORMES SOLAR project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BDPU SOLAR TORMES LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1906 Venus - 68091 Navarro
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DSWL_BES1
- POI Substation
- Venus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.