258.41 MW storage in Bexar, TX · In queue since September 2020 · Proposed COD December 2028
258.41 MW
Capacity
1
Components
Battery
5y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The BRP Denali BESS project is a proposed 258.41 MW battery storage project located in Bexar County, Texas. Developed by BRP Denali BESS LLC, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue as ERCOT-22INR0424 on September 25, 2020. The proposed commercial operation date is December 1, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists entirely of battery storage, with a total capacity of 258.41 MW. The point of interconnection is Tap 138kV 5395 Sommers - 5030 Braunig East. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Denali BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 5395 Sommers - 5030 Braunig East
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CALAVER_OWS1
- POI Substation
- O. W. Sommers Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about BRP Denali BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.