Ferdinand Grid BESS (ERCOT-22INR0422) — Project Summary

Queue ID
ERCOT-22INR0422
Capacity
205.5 MW
Technology
Battery
Status
active
Location
Bexar, TX
Region
ERCOT
Developer
Ferdinand Grid, LLC
IA Status
IA Executed

Ferdinand Grid BESS

ERCOT-22INR0422BetaActiveBatteryERCOTLBNL

205.5 MW storage in Bexar, TX · In queue since March 2021 · Proposed COD May 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

205.5 MW

Capacity

1

Components

Battery

5y 8m

In Queue

IA Executed

IA Phase

Signed Nov 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 8m

IA → COD

3y 6m

Total Duration

1y 8m

Schedule

7 months past proposed COD

Construction75%
Queue EntryMar 1, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 28, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-05-01

Queue history
22INR0422 · 59 monthly ERCOT reports, Feb 2021 – May 2026

Projected COD moved

3 times

May 2023 → May 2026

Net change

+36 months

first report to latest

Capacity

203 → 206 MW

changed in the reports

Latest stage

Commercial operation

last listed May 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 1, 2021
Facilities study approvedJun 16, 2025
Interconnection agreement signedNov 28, 2022
Approved for energizationJan 16, 2026
Approved for synchronizationFeb 13, 2026
Approved for commercial operationJun 9, 2026
On ERCOT's inactive listApr 2022 – Oct 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
May 2026
From queue filing
Developer in saved assessment
Ferdinand Grid, LLC
From queue filing
Status at research time
Active
Active — IA executed Nov 2022, no construction or financing announcements found in public record
Financing
Not recorded

Milestones in this assessment

IA executedNov 28, 2022Latest in this assessment

Generation Interconnection Agreement executed with CPS Energy

interchange.puc.texas.gov
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&FilingParty=cps%20energy&DocumentType=ALL&SortBy=FilingParty&SortOrder=Ascending
  2. cleanview.co/planned-battery-projects/TX/22INR0422/ferdinand-grid-bess
  3. interconnection.fyi/project/ercot-22inr0422

Commercial operation date: LBNL queue snapshot shows proposed COD of May 2026. No contradictory news sources found; Cleanview aggregator sites echo the same May 2026 date, likely derived from LBNL data. No press releases or developer announcements found for this specific project.

Developer: Only source is LBNL filing entity 'Ferdinand Grid, LLC'. No press releases, corporate announcements, or news coverage found identifying a parent company or operating entity. Search results show similar Bexar County projects by Eolian/CPS Energy but no connection to Ferdinand Grid.

Status: LBNL shows 'active' status with IA executed in November 2022. No news coverage of groundbreaking, financing, or construction activity. Project remains in queue but lacks public development signals.

About

Saved background

Generated Apr 10, 2026 · Predates May 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Ferdinand Grid BESS project is a proposed 201.2 MW battery storage project located in Bexar County, Texas. Developed by Ferdinand Grid, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-22INR0422. The project entered the queue on March 1, 2021, with a proposed commercial operation date of May 1, 2026. The interconnection agreement (IA) was executed on November 28, 2022.

The proposed project is linked to the existing Ferdinand Energy Center operating plant (EIA plant ID 68915). The Ferdinand Grid BESS project has been featured in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: May 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Bexar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Ferdinand Grid, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

5260 Leon Creek 138kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
LEONLCPCT1_2
POI Substation
Leon Creek Switchyard

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.